Punj Lloyd Refining References

From A Barrel Full
Jump to navigation Jump to search

Introduction

Punj Lloyd offers the complete range of planning, design, engineering, procurement and construction services in turnkey and composite construction projects.

+++ References

  1. Mangalore Refinery Project
    • Delayed Coker Unit
    • Mangalore Refinery Petrochemicals Ltd
    • Residual basic engineering, procurement, fabrication, erection, installation, construction, testing and pre-commissioning of four coke drums - 2,000 MT, 10 m dia x 41 m height.
    • Completed: 2011
  2. Mangalore Refinery Project
    • Petro Fluidised Catalyst Converter Unit
    • Mangalore Refinery/Engineers India Ltd
    • Fabrication and erection of piping, erection of equipment including heavy and super heavy lifts, structural work, painting, insulation, precommissioning/commissioning.
    • Completed: 2011
  3. Mangalore Refinery Project
    • Offsite for Phase III
    • Mangalore Refinery Petrochemicals Ltd
    • Transportation, shop and field fabrication and erection of piping A/G and U/G including specials, supporting, installation of online instruments, valves including chemical cleaning, flushing, NDT, hydro-testing and Commissioning.
    • Completed: 2011
  4. Exxon Singapore Refinery
    • SAR Revamp
    • Exxon Mobil Asia Pacific Pte Ltd/Foster Wheeler Asia Pacific Pte Ltd
    • Civil work including piling, excavation, roads, paving and mechanical work including piping fabrication and erection, equipment erection work, structural steel and support, NDT, PWHT, painting and insulation, OFC, switch gear extension and modification, instrumentation control for field instruments, control valves and turnaround activities during shutdown of the refinery.
    • Completed: 2010
  5. Gujarat Refinery Upgrade Project
    • Delayed Coker Unit and LPG Merox Block
    • Indian Oil Corporation Ltd
    • Residual basic and detailed engineering, procurement, construction and commissioning for 3.7 MMTPA delayed coker unit and 150 TMTPA LPG Merox unit.
    • Completed: Aug 2010
  6. Bina Refinery Project
    • Sulphur Block
    • Bharat Oman Refinery Ltd/Engineers India Ltd
    • Residual process design, detailed engineering, procurement, construction, fabrication, insulation, pre-commissioning and commissioning of Amine Regeneration Unit, Sour Water Strapper, Tail Gas Treating Unit and Sulphur Recovery Unit
    • Completed: Aug 2010
  7. Barauni Refinery Ms Quality Upgradation Project
    • MSQ Upgradation
    • Indian Oil Corporation Ltd/Toyo Engineering India Ltd
    • Residual basic and detailed engineering, procurement, construction and commissioning of reformate splitter unit, naphtha hydrotreating unit, isomerization unit and nitrogen generation unit.
      • Reformate Splitter Unit : 274,000 TPA
      • Naphtha Hydrotreating Unit : 183,000 TPA
      • C5 - C6 Isomerization Unit : 126,000 TPA
      • Prime G+ : 322,000 TPA+ : 81,000 TPA
      • Nitrogen Generation Unit : 850 Nm³/hr capacity
    • Completed: Aug 2010
  8. Haldia Refinery
    • Hydrocracker Unit
    • Indian Oil Corp Ltd/Lurgi India Co Ltd
    • Residual process design, detailed engineering, procurement, supply, third party inspection, transportation of all equipment/materials to site, materials management, construction, installation, testing, pre-commissioning, commissioning, performance guarantee run on single point responsibility basis. Capacity : 1.7 MMTPA
    • Completed: Feb 2010
  9. Haldia Refinery
    • Hydrogen Generation Unit
    • Indian Oil Corp Ltd/Lurgi India Co Ltd
    • Residual process design, detailed engineering, procurement, supply, transportation of all equipment/materials to site, materials management, construction including installation, testing, precommissioning, commissioning, performance guarantee run on single point responsibility basis. Capacity : 70 TTPA
    • Completed: Jan 2010
  10. Yemen Lng Terminal
    • Utilities and Offsites for LNG Plant
    • Yemen LNG Co Ltd/Yemgas (JV of Technip France, JGC Corp and Kellog Brown & Root)
    • Construction civil, pressurized underground piping, steel structure erection, hoisting and mechanical erection, above ground piping, electrical, instrumentation, painting, insulation of LNG Plant
    • Completed Sep 2009
  11. Onshore Gas Development Phase III Eastern
    • Bechtel Co Ltd/Abu Dhabi Gas Industries Ltd (GASCO)
    • Piping and equipment erection for offsites and utilities at Abu Dhabi.
    • Completed Aug 2009
  12. Al-Ruwais Refinery, UAE
    • Central Environment Protection Facility
    • SNC-Lavalin International/Abu Dhabi Oil Refining Co (Takreer)
    • Design, engineering, procurement, construction, commissioningand start-up of process piping and tankage for BeAAT project
    • Completed: Oct 2008
  13. Tengiz Oil Field
    • Second Generation Project Offsites and Utilities
    • Tengizchevroil/PFD International LLC (Parsons/Fluor Daniel JV)
    • Offsite and utilities mechanical work comprising equipment installation, piping fabrication, erection, insulation, painting, commissioning assistance for the following areas at Tengiz, Kazakhstan : Chemical Storage, Fuel Gas Compressor, Flare, Interconnecting Piperacks, LPG and Crude Storage Tanks, LACT (Lease Automatic Custody Transfer) Metre Water Treatment
    • Completed: Jun 2006
  14. Panipat Refinery
    • Paraxylene Unit No 2
    • Indian Oil Corp Ltd
    • Fabrication and erection of structural work, equipment, piping and painting
    • Completed: Jun 2006
  15. Haldia Refinery Motor Spirit Quality Upgrade Project
    • Motor Spirit Quality Upgradation
    • Indian Oil Corp Ltd/ Lurgi India
    • Residual process design, detailed engineering, procurement, construction and commissioning on EPC basis
      • Naphtha Splitter - 385,000 MT/YR
      • Naphtha Hydrotreater - 82,000 MT/YR
      • Reformate Splitter - 182,000 MT/YR
      • Isomerisation – LPG Recovery - 122,000 MT/YR
      • Selective Hydrogenation - 200,000 MT/YR
      • FCC Gasoline Splitter - 200,000 MT/YR
      • Prime G+ Selective Hydrodesulphurisation - 160,000MT/YR
      • Automatic on-line MS Blending Station (with optimisation)
    • Completed: Dec 2005
  16. Panipat Refinery
    • Hydrocracker Unit – 1.7 MMTPA
    • Daelim Industrial Co Ltd/Engineers India Ltd/Indian Oil Corp Ltd
    • Mechanical construction comprising erection of equipment including reactors, structural steel supply and fabrication, erection work, piping, fire-proofing and painting at
    • Completed: Sep 2005
  17. Peciko Gas Field
    • Peciko Onshore Development Phase 4 Indonesia
    • TotalFinaElf E&P Indonesie
    • Engineering, procurement and supply of materials, construction, pre-commissioning and commissioning assistance for two gas compression trains at onshore plant at Senipah on EPC basis, with a gas capacity of 450 MMSCFD for each train.
    • Completed: May 2005
  18. Chennai Refinery
    • Visbreaker Unit (VBU) and Sulphur Block
    • Petrofac International Ltd/Chennai Petroleum Corp Ltd
    • Residual process design, detailed engineering, procurement, construction and commissioning
      • VBU : 3600 mt/sd
      • SRU : 2 x 90 tpd
      • ARU : 330 tph
      • SWS : 58.9 mt/hr
    • Completed Aug 2003
  19. Guwahati Refinery
    • Sulphur Block and Utilities/Offsite
    • Siirtec Nigi S.p.A./Indian Oil Corp Ltd
    • Residual process design, detailed engineering, procurement, construction and commissioning on EPC basis
      • SRU : 5 tpd
      • ARU : 6.5 tph
      • SWS : 6 m3/hr
      • Extensive Utilities and Offsites
    • Completed: Dec 2001
  20. Mathura Refinery
    • Hydrocracker Unit - (1.2 MMTPA)
    • Indian Oil Corp Ltd
    • Erection of equipment, machinery, structural work, fabrication, erection of piping, electrical instrumentation, painting, insulation and fire-proofing for Hydrocracker Unit of Matching Secondary Processing Facilities
    • Completed: Jun 2000
  21. Kochi Refinery
    • Sulphur Block
    • Petrofac International Ltd/Kochi Refineries Ltd
    • Civil and structural work, erection of equipment, machinery, fabrication and erection of piping, tanks, electrical, instrumentation, painting, insulation and fire-proofing of the Sulphur Recovery Unit (2 x 72 TPD), Amine Regeneration Unit and Sour Water Stripper, including related supplies
    • Completed: Mar 2000
  22. Jamnagar Refinery I
    • Additional Chilling Train
    • Reliance Petroleum Ltd/Whessoe LGA
    • Residual engineering, procurement, construction and pre-commissioning of additional LPG/Propylene chilling train for LPG Storage.
    • Completed: Feb 2000
  23. Mathura Refinery
    • Sulphur Block
    • Petrofac International Ltd/Indian Oil Corp Ltd
    • Civil and structural work, erection of equipment, machinery, fabrication and erection of piping, tanks, electrical, instrumentation, painting, insulation and fire-proofing of the Sulphur Recovery Unit (3 x 60 TPD), Amine Regeneration Unit and Sour Water Stripper, including related supplies
    • Completed: Oct 1999
  24. Gujarat Refinery
    • MTBE Plant
    • Indian Oil Corp Ltd
    • Detailed and residual basic engineering, procurement, construction and commissioning of MTBE plant (37,000 TPA) on EPC basis
    • Completed: Sep 1999
  25. Visakhapatnam Refinery
    • CDU III, VDU III, VBU for VREP-II
    • Hindustan Petroleum Corp Ltd/Engineers India Ltd
    • Erection of CS, alloy steel and clad piping, mechanical equipment erection work for 3 MMTPA capacity expansion
    • Completed: Sep 1999
  26. Mumbai Refinery
    • Sulphur Block
    • Kinetic Technology Ltd/Hindustan Petroleum Corp Ltd
    • Civil and structural work, erection of equipment, machinery, fabrication and erection of piping, tanks, electrical, instrumentation, painting, insulation and fire-proofing of the Sulphur Recovery Unit (2 x 65 TPD), Amine Regeneration Unit and Sour Water Stripper, including related supplies
    • Completed: Aug 1999
  27. Gujarat Refinery
    • Sulphur Block
    • Petrofac International Ltd/Indian Oil Corp Ltd
    • Civil and structural work, erection of process equipment, machinery, fabrication and erection of piping, tanks, electrical, instrumentation, painting, insulation and fire-proofing of the Sulphur Recovery Unit (2 x 35 TPD), Amine Regeneration Unit and Sour Water Stripper, including related supplies
    • Completed: Jul 1999
  28. Jamnagar Refinery I
    • Piping Work
    • Reliance Petroleum Ltd
    • Fabrication and erection of piping (1,500,000 inch m) for marine tank farm area, fire water pump house and associated work at Reliance Refinery.
    • Completed Jul 1999
  29. Jamnagar Refinery I
    • Low Temperature LPG/Propylene Storage
    • Reliance Industries Ltd/Bechtel, UK
    • Residual engineering, procurement, construction for Propylene system package to convert pressurised LPG into cryogenic LPG, storage and re-liquification package including one double walled propylene storage system (26,000 m3) and allied mechanical, electrical, instrumentation and civil work
    • Completed: Jun 1999
  30. Gas Field Development at Dandewalan and Tanot in western Rajasthan
    • Oil India Ltd/Triune Projects
    • Detailed and residual basic engineering, procurement, construction, testing and commissioning of gas gathering stations and gas processing complex, (1.0 MMSCMD) SCADA system and other facilities required for the development of gas fields
    • Completed Mar 1997
  31. Ravva Oil and Gas Field
    • Oil Field Development
    • Hyundai Heavy Industries Ltd/Cairn Energy
    • Construction of onshore processing facility for oil and gas fields in S Yanam, including 6 Nos. oil storage tanks on stone column foundations, electrical and instrumentation work, equipment erection and onshore pipelines from the process plant to the landfall point.
    • Completed: Oct 1996
  32. Effluent Treatment Plant
    • Oil and Natural Gas Corp Ltd
    • Design, engineering, supply, erection and commissioning of 4,000 m3 per day effluent treatment plant at North Santhal
    • Completed: Aug 1996
  33. Navagam Oil Field
    • Fire Water System for Desalter Plant
    • Oil and Natural Gas Corp Ltd
    • Engineering, supply, erection and commissioning of fire water, storm water and electrical work
    • Completed: Jan 1995
  34. Navagam Oil Field
    • Integration System for Desalter Plant
    • Oil and Natural Gas Corp Ltd/Engineers India Ltd
    • Engineering, supply, erection and commissioning of integration systems covering civil, mechanical, piping, electrical and instrumentation work
    • Completed: Jan 1995
  35. Natural Gas Compressor Station
    • Oil and Natural Gas Corp Ltd
    • Design, engineering, supply, erection and commissioning of 10 Nos. reciprocating compressors, each of 50,000 Nm3 per day capacity, with all utilities, including an 11 KV substation at Kalol and South Santhal.
    • Completed: Jan 1994
  36. Auriya Compressor and Terminal Station
    • Spie Capag/NKK/Toyo Consortium
    • Complete mechanical work, including equipment erection, piping, painting and insulation of compressor station for HBJ Gas Pipeline at Auriya.
    • Completed Apr 1989