Introduction
+
=== Introduction ===
  
 
* Since 1991, Offshore & Engineering Division has become a world leading EPIC contractor providing integrated services such as Engineering, Procurement, Construction, Transportation, Installation, Offshore Hook-up and Commissioning, and Project Management.  
 
* Since 1991, Offshore & Engineering Division has become a world leading EPIC contractor providing integrated services such as Engineering, Procurement, Construction, Transportation, Installation, Offshore Hook-up and Commissioning, and Project Management.  
 
* Offshore & Engineering Division has successfully completed more than 170 projects including over 100 EPIC projects in turn-key basis and has been recognized as one of the most experienced and advanced offshore yards in the world. The range of products and services covers FPSOs, FLNGs, FPUs, semisubmersibles, jack-ups, TLPs, fixed platforms, subsea pipelines, and land-based LNG and processing modules.
 
* Offshore & Engineering Division has successfully completed more than 170 projects including over 100 EPIC projects in turn-key basis and has been recognized as one of the most experienced and advanced offshore yards in the world. The range of products and services covers FPSOs, FLNGs, FPUs, semisubmersibles, jack-ups, TLPs, fixed platforms, subsea pipelines, and land-based LNG and processing modules.
  
+++ References
+
=== References ===
  
++++ FPSO's
+
==== FPSO's ====
  
  
Line 46: Line 46:
 
#* EPC
 
#* EPC
 
#* Jan. 2004 - Apr. 2007
 
#* Jan. 2004 - Apr. 2007
#* Oil Production : 250,000 Bopd, Total : 72,700 M/T, Topsides : Ic Gas Production : 8 Mmscmd, Storage Capacity : 2.0 Mmbbl, Accommodation : 120 Men
+
#* Oil Production: 250,000 Bopd, Total : 72,700 M/T, Topsides : Ic Gas Production : 8 Mmscmd, Storage Capacity : 2.0 Mmbbl, Accommodation : 120 Men
# [[AKPO FPSO]]  
+
# '''[[Akpo FPSO]]'''
 
#* Total  
 
#* Total  
 
#* 310m X 61m X 31m  
 
#* 310m X 61m X 31m  
 
#* May 2005 - Nov. 2008
 
#* May 2005 - Nov. 2008
 
#* L/Q Spread Moored, Total : 98,450 M/T  
 
#* L/Q Spread Moored, Total : 98,450 M/T  
# Moho Bilondo FPU TOTAL E & P Congo Congo FPU : 188.5 m x 34 m x 12.5 m EPIC Jun. 2005 ~ Feb. 2008 28,433
+
# [[Moho Bilondo Oil Field]]
# Usan FPSO TOTAL Nigeria FPSO : 320 m x 61 m x 32 m EPC Feb. 2008 ~ Nov. 2012 114,092
+
#* TOTAL E & P
# Goliat FPSO Eni Norge AS Norway FPSO : 90 m x 75 m (Cylindrical Type) 14 EPC Feb. 2010 ~ Apr. 2015 51,384
+
#* Congo
# Quad 204 FPSO BP North Sea FPSO : 270 m x 52 m x 30 m EPC Feb. 2011 ~ Dec. 2015 84,424
+
#* FPU : 188.5 m x 34 m x 12.5 m, 28,433t
# Rosebank FPSO Chevron UK FPSO : 292 m x 57.4 m x 30 m EPC Apr. 2013 ~ Dec. 2019 99,754
+
#* EPIC
 
+
#* Jun. 2005 ~ Feb. 2008  
 +
# [[Usan FPSO]]
 +
#* TOTAL
 +
#* Nigeria
 +
#* FPSO : 320 m x 61 m x 32 m, 114,092t
 +
#* EPC  
 +
#* Feb. 2008 ~ Nov. 2012  
 +
# [[Goliat FPSO]]
 +
#* Eni Norge
 +
#* Norway
 +
#* FPSO : 90 m x 75 m (Cylindrical Type), 51,384t
 +
#* EPC  
 +
#* Feb. 2010 ~ Apr. 2015  
 +
# [[Glen Lyon FPSO]]
 +
#* BP  
 +
#* UK
 +
#* FPSO : 270 m x 52 m x 30 m 84,424t
 +
#* EPC  
 +
#* Feb. 2011 ~ Dec. 2015  
 +
# [[Rose Bank FPSO]]   
 +
#* Chevron
 +
#* UK
 +
#* FPSO: 292 m x 57.4 m x 30 m, 99,754t
 +
#* EPC
 +
#* Apr. 2013 ~ Dec. 2019
  
++++ Others
+
==== Others ====
  
 
# [[Amenam Kpono Oil Field | Amenam/Kpono FSO]]
 
# [[Amenam Kpono Oil Field | Amenam/Kpono FSO]]
Line 83: Line 107:
 
#* Epic  
 
#* Epic  
 
#* Jun. 2005 - Feb. 2008
 
#* Jun. 2005 - Feb. 2008
# [[Troll Oil And Gas Field | Troll-C FPU]]  
+
# '''[[Troll Oil and Gas Field | Troll-C FPU]]'''
 
#* Hull Construction  
 
#* Hull Construction  
 
#* Norsk Hydro  
 
#* Norsk Hydro  
Line 90: Line 114:
 
#* Apr. 1997 - Nov. 1998  
 
#* Apr. 1997 - Nov. 1998  
 
#* (Gva 8000) - Contractor : Umoe Haugesung  
 
#* (Gva 8000) - Contractor : Umoe Haugesung  
# Delta House FPS Hull LLOG GoM Semisub FPS : 81.6 m x 81.6 m x 51.6m 16 ePC Aug. 2012 ~ Feb. 2014 11,372
+
# [[Delta House Oil and Gas Field]] - FPS Hull
# Aasta Hansteen Spar Hull Statoil Norway Spar Hull : 196 m (H), 50 m (D) EPC Aug. 2012 ~ Mar. 2016 45,332
+
#* LLOG
# Aasta Hansteen Topside Statoil Norway Topside : 60 m x 50 m x 18 m EPC Jan. 2013 ~ Apr. 2017 21,500
+
#* GoM
# Moho Nord TLP EPSCC (Ph.3) Total E&P Congo Congo Tension Leg Platform : 61.5 m x 61.5 m 19 EPC Feb. 2013 ~ Nov. 2015 14,570
+
#* Semisub FPS: 81.6 m x 81.6 m x 51.6m 11,372t
# Moho Nord FPU Total E&P Congo Congo FPU : 250 m x 44 m x 18 m EPC Mar. 2013 ~ Jun. 2016 62,200
+
#* ePC  
# Jangkrik FPU Hull / LQ Eni Indonesia Hull :200 m x 46 m x 15 m EPC Feb. 2014 ~ Mar. 2016 28,745
+
#* Aug. 2012 ~ Feb. 2014  
 
+
# '''[[Aasta Hansteen Gas and Condensate Field]]''' - Spar Hull
 +
#* Statoil
 +
#* Norway  
 +
#* Spar Hull : 196 m (H), 50 m (D)  
 +
#* EPC  
 +
#* Aug. 2012 ~ Mar. 2016  
 +
#* 45,332 M/T
 +
# '''[[Aasta Hansteen Gas and Condensate Field]]''' - Topside
 +
#* Statoil
 +
#* Norway  
 +
#* Topside: 60 m x 50 m x 18 m  
 +
#* EPC  
 +
#* Jan. 2013 ~ Apr. 2017  
 +
#* 21,500 M/T
 +
# '''[[Moho Bilondo Oil Field]]'''
 +
#* Moho Nord TLP EPSCC (Ph.3)  
 +
#* Total E&P  
 +
#* Congo
 +
#* Tension Leg Platform: 61.5 m x 61.5 m 19  
 +
#* EPC  
 +
#* Feb. 2013 ~ Nov. 2015  
 +
#* 14,570 M/T
 +
# '''[[Moho Bilondo Oil Field]]'''
 +
#* Moho Nord FPU
 +
#* Total E&P  
 +
#* Congo
 +
#* FPU: 250 m x 44 m x 18 m  
 +
#* EPC  
 +
#* Mar. 2013 ~ Jun. 2016
 +
#* 62,200 M/T
 +
# '''[[Jangkrik Gas Field]]'''
 +
#* Jangkrik FPU Hull / LQ
 +
#* Eni
 +
#* Indonesia
 +
#* Hull :200 m x 46 m x 15 m
 +
#* EPC
 +
#* Feb. 2014 ~ Mar. 2016
 +
#* 28,745 M/T
  
++++ Links
+
==== Links ====
  
 
* [http://english.hhi.co.kr/biz/offshore_over Hyundai Offshore & Engineering]
 
* [http://english.hhi.co.kr/biz/offshore_over Hyundai Offshore & Engineering]

Latest revision as of 14:20, 11 July 2024

Introduction

  • Since 1991, Offshore & Engineering Division has become a world leading EPIC contractor providing integrated services such as Engineering, Procurement, Construction, Transportation, Installation, Offshore Hook-up and Commissioning, and Project Management.
  • Offshore & Engineering Division has successfully completed more than 170 projects including over 100 EPIC projects in turn-key basis and has been recognized as one of the most experienced and advanced offshore yards in the world. The range of products and services covers FPSOs, FLNGs, FPUs, semisubmersibles, jack-ups, TLPs, fixed platforms, subsea pipelines, and land-based LNG and processing modules.

References

FPSO's

  1. P-33 FPSO
    • Conversion Of V.L.C.C. “Henrique Dias”
    • Petrobras
    • 320m X 54.5m X 27.8m
    • EPIC
    • Apr. 1996 - Jun. 1998
    • Oil Production : 50,000 Bopd, Total : 279,749 M/T, Gas Compression : 2.0 Mmscmd, Class : Abs Class, Storage Capacity : 2.0 Mmbbl, Offloading : 150,000 Bopd
  2. P-35 FPSO
    • Conversion Of V.L.O.O. “Jose Bonifacio”
    • Petrobras
    • 320m X 54.5m X 28m
    • EPIC
    • Jun. 1996 - Dec. 1998 Oil Production
    • 100,000 bpd, Dead Weight : 270,358 M/T Gas Compression : 3.0 Mmscmd, Class : Abs Class, Storage Capacity : 2.0 Mmbbl, Offloading : 150,000 bpd
  3. Girassol FPSO
    • Total
    • 300m X 59.6m X 30.5m
    • EPIC
    • Jun. 1999 - Feb. 2001
    • Oil Production : 200,000 Bopd, Dead Weight : 343,000 Dwt, Water Injection : 250,000 Bwpd, Total : 60,000 M/T Storage Capacity : 2.0 Mmbbl, Accommodation : 140 Men
  4. Kizomba A FPSO
    • Exxon
    • 285m X 63m X 32.2m
    • EPC
    • Jul. 2001 - Jun. 2004
    • Oil Production : 250,000 Bopd, Total : 80,661 M/T, Gas Production : 400 Mmcfd, Storage Capacity : 2.2 Mmbbl, Accommodation : 100 Men
  5. Kizomba B FPSO
    • Exxon
    • 285m X 63m X 32.2m
    • EPC
    • Dec. 2002 - Oct. 2005
    • Oil Production : 250,000 Bopd, Total : 80,661 M/T, Gas Production : 400 Mmcfd, Storage Capacity : 2.2 Mmbbl, Accommodation : 100 Men
  6. Greater Plutonio FPSO
    • BP
    • 310m X 58m X 32m
    • EPC
    • Jan. 2004 - Apr. 2007
    • Oil Production: 250,000 Bopd, Total : 72,700 M/T, Topsides : Ic Gas Production : 8 Mmscmd, Storage Capacity : 2.0 Mmbbl, Accommodation : 120 Men
  7. Akpo FPSO
    • Total
    • 310m X 61m X 31m
    • May 2005 - Nov. 2008
    • L/Q Spread Moored, Total : 98,450 M/T
  8. Moho Bilondo Oil Field
    • TOTAL E & P
    • Congo
    • FPU : 188.5 m x 34 m x 12.5 m, 28,433t
    • EPIC
    • Jun. 2005 ~ Feb. 2008
  9. Usan FPSO
    • TOTAL
    • Nigeria
    • FPSO : 320 m x 61 m x 32 m, 114,092t
    • EPC
    • Feb. 2008 ~ Nov. 2012
  10. Goliat FPSO
    • Eni Norge
    • Norway
    • FPSO : 90 m x 75 m (Cylindrical Type), 51,384t
    • EPC
    • Feb. 2010 ~ Apr. 2015
  11. Glen Lyon FPSO
    • BP
    • UK
    • FPSO : 270 m x 52 m x 30 m 84,424t
    • EPC
    • Feb. 2011 ~ Dec. 2015
  12. Rose Bank FPSO
    • Chevron
    • UK
    • FPSO: 292 m x 57.4 m x 30 m, 99,754t
    • EPC
    • Apr. 2013 ~ Dec. 2019

Others

  1. Amenam/Kpono FSO
    • Total
    • 298m X 62m X 32m
    • EPC
    • Sep. 2000 - Dec. 2002
    • Storage Capacity : 2.4 Mmbbl, Total : 43,500 M/T (T & I : Sbm) Displacement : Max. 340,000dwt, Design Life : 25 Years
  2. Na Kika Semi-Submersible FPU
    • Shel
    • 31,609 M/T
    • PCT
    • Feb 2001 - Jan. 2003 Oil Production, Gas Production : 325 Mmcfd
  3. West Seno FP
    • Unocal
    • 152m X 38m X 10m
    • EPIC
    • Aug. 2001 - Jul. 2003
    • Tlp : 50m X 50m X 40m Pipeline (2 Lines) : 12” X 62 Km, Total : 28,350 M/T
  4. Moho Bilondo FPU
    • Total
    • 188.5m X 34m X 12.5m
    • Epic
    • Jun. 2005 - Feb. 2008
  5. Troll-C FPU
    • Hull Construction
    • Norsk Hydro
    • 14,100 M/T
    • EPCT
    • Apr. 1997 - Nov. 1998
    • (Gva 8000) - Contractor : Umoe Haugesung
  6. Delta House Oil and Gas Field - FPS Hull
    • LLOG
    • GoM
    • Semisub FPS: 81.6 m x 81.6 m x 51.6m 11,372t
    • ePC
    • Aug. 2012 ~ Feb. 2014
  7. Aasta Hansteen Gas and Condensate Field - Spar Hull
    • Statoil
    • Norway
    • Spar Hull : 196 m (H), 50 m (D)
    • EPC
    • Aug. 2012 ~ Mar. 2016
    • 45,332 M/T
  8. Aasta Hansteen Gas and Condensate Field - Topside
    • Statoil
    • Norway
    • Topside: 60 m x 50 m x 18 m
    • EPC
    • Jan. 2013 ~ Apr. 2017
    • 21,500 M/T
  9. Moho Bilondo Oil Field
    • Moho Nord TLP EPSCC (Ph.3)
    • Total E&P
    • Congo
    • Tension Leg Platform: 61.5 m x 61.5 m 19
    • EPC
    • Feb. 2013 ~ Nov. 2015
    • 14,570 M/T
  10. Moho Bilondo Oil Field
    • Moho Nord FPU
    • Total E&P
    • Congo
    • FPU: 250 m x 44 m x 18 m
    • EPC
    • Mar. 2013 ~ Jun. 2016
    • 62,200 M/T
  11. Jangkrik Gas Field
    • Jangkrik FPU Hull / LQ
    • Eni
    • Indonesia
    • Hull :200 m x 46 m x 15 m
    • EPC
    • Feb. 2014 ~ Mar. 2016
    • 28,745 M/T