Difference between revisions of "Rijeka Refinery Delayed Coker Project"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
Line 36: | Line 36: | ||
=== History === | === History === | ||
* 2014 - Bechtel technology chosen for Coker | * 2014 - Bechtel technology chosen for Coker | ||
− | * 2019 - | + | * 2019 - Kinetics Technology awarded EPC contract |
=== Other Information === | === Other Information === |
Latest revision as of 07:18, 18 March 2020
Contents
Summary Information
- Ownership: INA (MOL)
- Website: http://www.ina.hr/
- Wiki Page: Rijeka Refinery
- Location: Rijeka, Croatia
- Capacity: million tons/annum & bbl/day
- Nelson Complexity:
- Project Stage: Under construction
- Expected Completion: 2023
- Budget: EUR 450 million
The Project
- Project Type: Upgrade
- Project Summary:
- The Project includes the debottlenecking of existing units and construction of new ones
- The delayed coker involves construction of the unit itself as well as solutions for coke storage and sea jetty construction
- Main Contractors:
- Kinetics Technology: EPC contract on a Lump Sum Turnkey basis
- engineering, procurement of all equipment and materials, construction and erection work for a new Delayed Coking Unit with coke handling and ship loading, Sour Water Stripper, Amine Recovery units and the revamping of Hydrocracker, Sulphur Recovery, and Utilities & Offsites units.
- Licences:
- Bechtel: Licence for Delayed coking unit
Refining Units
- Delayed Coker
- Sour Water Stripper
- Amine Recovery units
- Hydrocracker, Sulphur Recovery (Revamping)
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
- -
Products Produced
- The refinery will no longer produce residual fuel oil
History
- 2014 - Bechtel technology chosen for Coker
- 2019 - Kinetics Technology awarded EPC contract
Other Information
- The project was significantly delayed due to political problems between MOL, the main shareholder and the Croatian government