  • Neftochim Burgas Refinery
    • FCC Unit Revamping
    • Status: Ongoing
    • Scope of work: Engineering Procurement Construction (EPC)
    • Country: Bulgaria
    • Client: Lukoil Neftohim Burgas AD
    • Capacity: 250 t/h
    • Contractor: KT - Kinetics Technology
  • Rijeka Refinery Delayed Coker Project
    • New Delayed Coking Unit Complex
    • Status: Ongoing
    • Scope of work: Engineering, Procurement, Construction (EPC)
    • Country: Croatia
    • Client: INA - Industrija Nafte d.d.
    • Capacity: DCU 103 t/h, Revamp HCU 7,643 t/d, SRU 95 t/d
    • Contractor: KT - Kinetics Technology
  • Luanda Refinery Upgrade Project
    • Engineering, Procurement, Construction, Installation And Commissioning Of A New Platforming Unit
    • Status: Ongoing
    • Scope of work: EPC
    • Country: Angola
    • Client: Eni Angola Exploration B.V. for Sonarel Refinery
    • Capacity: NHT 1,500 t/d , Platforming 1,100 t/d
    • Contractor: KT - Kinetics Technology
  • Nizhny Novgorod Refinery Coker Project
    • Refinery Off Gas
    • Status: Ongoing
    • Scope of work: EPC
    • Country: Russia
    • Client: Lukoil Nizhegorodnefteorgsintez
    • Capacity: 60,000 Nm3/h
    • Contractor: KT - Kinetics Technology
  • Nizhny Novgorod Refinery Coker Project
    • Gas Fractionation Unit
    • Status: Ongoing
    • Scope of work: EPC
    • Country: Russia
    • Client: Lukoil Nizhegorodnefteorgsintez
    • Capacity: 425,000 t/y
    • Contractor: KT - Kinetics Technology
  • Iplom Busalla Refinery
    • Mild Hydrocracking Unit
    • Status: Completed
    • Scope of work: EPC
    • Country: Italy
    • Client: IPLOM
    • Capacity: 1,400 t/d vacuum gasoil
    • Contractor: KT - Kinetics Technology
  • Milazzo Refinery
    • Vacuum Unit Refining
    • Status: Completed
    • Scope of work: Services for EPC
    • Country: Italy
    • Client: Raffineria di Milazzo
    • Capacity: 11,000 t/d
    • Contractor: KT - Kinetics Technology
  • Total Antwerp Refinery
    • Refinery Off Gas (Rog) Revamp And Interconnecting Lot B
    • Status: Completed
    • Scope of work: EPC (a) LS
    • Country: Belgium
    • Client: Total Olefins Antwerp
    • Capacity: 240 t/h
    • Contractor: KT - Kinetics Technology
  • Total Antwerp Refinery
    • Refinery Off Gas (ROG)
    • Status: Completed
    • Scope of work: EPC
    • Country: Belgium
    • Client: Total Olefins Antwerp
    • Capacity: 1 saturated gas train 39 t/h off gas, 1 unsaturated gas train 30 t/h off gas
    • Contractor: KT - Kinetics Technology
  • Limbe Refinery Project
    • Sonara Phase II Expansion Project: Hydrocracker
    • Status: Ongoing
    • Scope of work: EPC
    • Country: Cameroon
    • Client: Societe Nationale de RAffinage (SONARA)
    • Capacity: 800,000 t/y
    • Contractor: Consortium with KT CAMEROUN
  • Gdansk Refinery
    • Hydrowax Vacuum Distillation Unit
    • Status: Completed
    • Scope of work: EPC
    • Country: Poland
    • Client: LOTOS Asfalt SP. ZO.O
    • Capacity: 2,280 t/y
    • Contractor: KT - Kinetics Technology
  • Gdansk Refinery Coker Project EFRA
    • Coker Naphtha Hydrotreater Unit
    • Status: Completed
    • Scope of work: EPC
    • Country: Poland
    • Client: LOTOS Asfalt SP. ZO.O
    • Capacity: 18,000 t/y
    • Contractor: KT - Kinetics Technology
  • Gdansk Refinery Coker Project EFRA
    • Delayed Coking Unit
    • Status: Completed
    • Scope of work: EPC
    • Country: Poland
    • Client: LOTOS Asfalt SP. ZO.O
    • Capacity: 350,000 t/y
    • Contractor: KT - Kinetics Technology
  • Heydar Aliyev Baku Refinery Modernisation Project
    • Modernization And Reconstruction Project 2
    • Status: Ongoing
    • Scope of work: EPC
    • Country: Azerbaijan
    • Client: State Oil Company of Azerbaijan Republic (SOCAR)
    • Capacity: SRU No. 2 x 30 t/d each, TGT 1 x 40 t/d
    • Contractor: JV TCM/KT
  • Heydar Aliyev Baku Refinery Modernisation Project
    • Modernization And Reconstruction Project
    • Status: Completed
    • Scope of work: Licence + BEDP
    • Country: Azerbaijan
    • Client: State Oil Company of Azerbaijan Republic (SOCAR)
    • Capacity: SRU 2 x 30 t/d, TGT 1 x 40 t/d
    • Contractor: KT - Kinetics Technology

Refining ENGINEERING SERVICES FOR TECHNOLOGICAL INTEGRATION STC-CPO Status: Completed Scope of work: E Country: Italy Client: Eni SpA Capacity: - Contractor: KT - Kinetics Technology

  • Rabigh Refinery
    • Naphtha Hydrotreater'
    • Status: Ongoing
    • Scope of work: EPC
    • Country: Saudi Arabia
    • Client: Petro Rabigh (JV Saudi Aramco & Sumitomo Chemical)
    • Capacity: 17,000 BPD
    • Contractor: KT - Kinetics Technology

Refining SUPPLY OF THERMAL REACTOR PACKAGE Status: Ongoing Scope of work: EP Country: Azerbaijan Client: State Oil Company of Azerbaijan Republic (SOCAR) Capacity: 30 t/y Contractor: JV TCM/KT

Refining DIESEL FUEL HYDROTREATER UNIT Status: Ongoing Scope of work: EPC Country: Russia Client: Lukoil Nizhnegorodnefteorgsintez Capacity: 1,530 t/y Contractor: KT - Kinetics Technology

Refining FEASIBILITY STUDY FOR CONSTRUCTION OF OIL REFINERY PLANT WITH CRUDE OIL SUPPLY PIPELINE Status: Completed Scope of work: FS Country: Mongolia Client: Mongol Refinery LLC Capacity: 4,600 t/d Contractor: KT - Kinetics Technology

Refining NEW PROPANE PROPYLENE SPLITTER UNIT Status: Ongoing Scope of work: EPC Country: Croatia Client: INA Industrija Nafte d.d. Capacity: 10 t/h Contractor: KT - Kinetics Technology

Refining Refinery Off Gas (ROG) Project Belgium Status: Completed Scope of work: Engineering, Procurement, Construction (EPC) Country: Belgium Client: TOTAL Olefins Antwerp (Total Group) Capacity: 1 saturated gas train 39 t/h off gas, 1 unsaturated gas train 30 t/h off gas Contractor: KT - Kinetics Technology

PETROTER GAS TREATMENT AND UPGRADING KOHTLA JARVE GAS PLANT Status: Completed Scope of work: BEDP Country: Estonia Client: Viru Keemia Grupp AS (VKG) Capacity: 5,000 BPSD Contractor: KT - Kinetics Technology

Refining HIGH DENSITY POLYETHYLENE PLANT Status: Completed Scope of work: EP Country: Azerbaijan Client: SOCAR POLYMER LLC Capacity: PP 180,000 t/y, HDPE 120,000 t/y Contractor: KT - Kinetics Technology