Wilhelmshaven Floating LNG Terminal

From A Barrel Full
Jump to navigation Jump to search

Summary Information

  • Ownership: Uniper
  • Website: https://www.uniper.energy/
  • Location: Wilhelmshaven,
  • Capacity: 6 million tons/annum
  • Status: Under construction

Brief Description

  • The terminal consists of an FSRU, and a 30 km pipeline to connect it to the grid.
  • The FRSU will have a total natural gas-send-out capacity of up to 7.5 bcm/a and an LNG storage capacity of 174,000 m³

Technical Details

  • Storage capacity: 174,000 m³
  • Unloading capacity:
  • Send out capacity: 7.5 bcm/a
  • Constructor:

Ongoing Projects/Project Status

  • Uniper management expect the project to be completed by 2023 at the latest
  • The FRSU is supplied by Dynagas

Suppliers / Customers

  • Suppliers: Venture Global supplied the first cargo from the Calcasieu Pass LNG Export Terminal Project
  • Customers: An approximately 30 km long high-pressure gas pipeline will connect the FSRU to the natural gas pipeline network of Open Grid Europe (OGE)

History

  • 2022 - Uniper leases the FSRU
  • 2022 - Permits awarded for project construction
  • 2023 - The first commercial cargo arrived
  • 2024 - KN took over management of the terminal

Other Information

-

Links

  1. Dynagas Ltd. and Uniper facilitated the charter of two FSRUs for Germany
  2. Construction of Wilhelmshaven LNG terminal can start quickly
  3. First LNG cargo arrives at Germany's LNG terminal in Wilhelmshaven
  4. KN Becomes Commercial Manager of Four German LNG Terminals