Terra Nova Oil Field

From A Barrel Full
Jump to navigation Jump to search

Summary Information

  • Operator: Suncor
  • Country: Canada
  • Location: 350 kilometres southeast off the coast of Newfoundland and Labrador
  • Production start: 2002
  • Partners:
    • Suncor Energy 48% (operator)
    • Cenovus - 34%
    • Murphy Oil - 18%
  • Type: Oil
  • Estimated Reserves:
  • Production Volume:

Description

  • Suncor Energy operates the Terra Nova field, which is located approximately 350 kilometres southeast off the coast of Newfoundland and Labrador.
  • Discovered in 1984, the field was the second to be developed off Canada’s East Coast. Production from the field began in 2002, through the use of a Floating, Production Storage and Offloading (FPSO) vessel, the Terra Nova FPSO
  • The development has a total of 24 wells – 14 producers, seven water injection and three gas injection wells
  • This was the first development in North America to use FPSO technology in a harsh weather environment.
  • The field produces light sweet crude oil

Contractors

  • **Fluor Daniel Canada, Inc.:** The overall project manager provided engineering and construction services to the project.
  • **Maersk Company Canada Limited**, a leader in the exploration for and production of oil & gas, shipbuilding, aviation, and electronic data process services.
  • **Bouygues Offshore**, one of the world's largest construction conglomerates known for its unparalleled experience in the design and construction of concrete floaters, both semi-submersible and mono-hull.
  • **Emtunga:** Additional LQ cabin module
  • Subsea Technologies and Reservoir Team (START), an alliance between Schlumberger Oilfield Services Newfoundland, ABB Vetco Gray Canada and Baker Hughes Canada, will provide world-class integrated well services, well construction and subsea capabilities.
  • **Global Maritime:** Warranty surveyor and marine consultant for infield pipelines and associated subsea structures

History

  • 1984 - Terra Nova field discovered
  • 1996 - Petro-Canada Selects Alliance Newfoundland To Perform Design Study
  • 1997 - Environmental Assessment Agency granted approval
  • 1999 - Husky issued Terra Nova Bonds were originally issued for U.S.$250 million
  • 2002 - First production
  • 2006 - Major overhaul of the FPSO
  • 2019 - The field was shut down for the life extension project
  • 2020 - Cenovus merges with Husky and becomes a partner
  • 2021 - Cenovus increased its stake to 34%
  • 2023 - Production restarted

Geology

Links

  1. Terra Nova, Suncor
  2. Emtunga Offshore Platform References
  3. Global Maritime Pipeline References
  4. Petro-Canada Selects Alliance Newfoundland To Perform Design Study For The Terra Nova Oil Field Development
  5. Terra Nova Review Panel Recommends Go-Ahead with Conditions
  6. Terra Nova starts producing
  7. Husky Energy Redeems Terra Nova Bonds
  8. Terra Nova back in production
  9. [1]
  10. Cenovus announces Atlantic assets restructuring plan Cenovus and Husky Combine to Create a Resilient Integrated Energy Leader
  11. Suncor Energy Announces Restart of Production at Terra Nova