PM-3 CAA Oil And Gas Fields
Jump to navigation
Jump to search
Summary Information
- Operator: Repsol
- Country: Malaysia
- Location: PM-3
- Production start: 1997
- Partners:
- Type: Oil & Gas
- Estimated Reserves:
- Production Volume:
Description
- The PM-3 CAA project, which involves development of the West Bunga Kekwa, East Bunga Kekwa-Cai Nuoc, East Bunga Raya, West Bunga Raya, NW Bunga Raya, Bunga Tulip and Bunga Seroja fields
- Four wellhead platforms, a central processing platform, compression annex platform, floating storage offloading vessel and inter-field pipelines have been installed.
- These facilities have a production capacity of 60,000 bbls/d of oil and 270 mmcf/d of gas.
- The Bunga Orkid/Bunga Pakma gas field complex was developed as phase three and includes Bunga Orkid-A platform and FSO Orkid
- Gas is supplied via a 24-inch 170 km pipeline from PM-3 CAA to the Resak Platform
Contractors
- **MMCOG:**
- Detailed Design of Bunga Kekwa 'C' (BK-C) Annex Topside
- Detailed Design of Bunga Kekwa 'C' (BK-C) Annex Substructure
- **Hyundai Heavy Industries:** Phase 2 Topside
- **FoundOcean:** Bunga Raya 'A'
- Omni Offshore: Provision of the FSO
- **MMHE:**
- B. Raya E - Jacket
- Conversion of FSO Orkid
- **SDE:** Bunga Raya E - Deck, Topside
- **Kavin Engineering:** TML Bunga RAYA-A (BR-A) Platform, Sand Cleaning System
- **Petrofac RNZ:** Bunga Tulip “A” Development
- **Bluewater:** External Turret Mooring system for FSO Orkid
- **BC Petrochemical:** Chemical Injection System
- **ICON Engineering:**
- Conceptual design & installation engineering, followed by the structural & geotechnical detailed design for the BR-A Annexe Monopods
- Bunga Kekwa C Annexe Platform, Conceptual Design and Installation
History
- 1997 - Phase 1 oil production commenced
- 2003 - phase 2 start up
- 2006 - Bunga Tulip came onstream
- 2008 - FSO Orkid was completed
- 2009 - Phase 3 production starts
- 2014 - Repsol acquired Talisman and became a partner
Geology
Links
- Anggerik Laksana Platform References
- Aquila Mooring Solutions FPSO References
- BC Petrochemical Oil And Gas Processing References
- Bluewater Mooring References
- Fiberbond Offshore Platform References
- FoundOcean Subsea References
- Hyundai Heavy Industries Platform References
- Icon Engineering Platform References
- Jotun Platform References
- Kavin Engineering Oil And Gas Processing References
- Misc FPSOs And Platforms
- MMCOG Platform References
- Omni Offshore Floating Terminal References
- Petrofac-RNZ Offshore and Platform References
- Talisman Announces First Oil From The PM-3 CAA Phase 2 & 3 Project In The Overlapping Area Between Malaysia And Vietnam
- MMHE Completed Another Conversion
- FSO Orkid successfully received first oil
- Repsol reaches an agreement with Talisman Energy to acquire the Canadian oil company