P-75 FPSO

From A Barrel Full
Jump to navigation Jump to search

Summary Information

Brief Description

  • P-75 produces through ten producing wells, also using seven injection wells. Relief vessels will be used to offload the oil production, while gas will be drained by pre-salt pipeline routes.
  • It was the second platform completed for the exploration of the pre-salt fields located in the Transfer of Rights region. The platform will be capable of producing up to 150,000 barrels/day and of compressing 7 million cubic meters of natural gas/day
  • The vessel is a converted VLCC

Contractors

  • **Norberto Odebrecht / UTC Engenharia:** Hull conversion
  • **GE Oil & Gas:** Supply of gas turbines and electric generators, turbocompression trains and electric motor driven compressors for gas main, export services and CO2 re-injection

Status

  • In operation

History

  • 2012 - Norberto Odebrecht & UTC Engenharia awarded hull conversion contracts
  • 2013 - GE awarded turbines & Compressors contract
  • 2018 - The vessel arrived at the field

Other Information

  • -

Links

  1. Petrobras signs agreement to convert platform hulls for transfer of rights areas
  2. GE Oil & Gas Wins US$500 Million Petrobras Contract
  3. Start-up of P-75 in Búzios field pre-salt of Santos Basin