Mimas and Tethys Gas Fields
Jump to navigation
Jump to search
Summary Information
- Operator: Harbour Energy
- Country: UK
- Location: Southern North Sea
- Production start:
- Partners:
- Type: Gas
- Estimated Reserves:
- Production Volume:
Description
- The Mimas & Tethys are two Southern North Sea gas developments in blocks 48/9a and 49/11b respectively.
- Mimas is linked by a 13.5km, 10” export pipeline to the Saturn platform that is tied back to the existing Lincolnshire Offshore Gas Gathering System (Loggs).
- Export gas from Tethys is transported via a new 10” pipeline to the Saturn-LOGGS pipeline.
Contractors
- **Seaway Heavy Lifting:** Transport & Installation
- **KWSubsea:** Detailed design of pipeline
- **Micoperi:** Installation of subsea pipeline 10” plus 3” piggy back 17 km long
- **FoundOcean:** Grouting
- **Global Maritime:** Warranty surveyor for installation of flowlines
History
- 1989 - Mimas field discovered
- 2006 - Government approval granted for development
- 2007 - Both platforms installed
- 2019 - Chrysaor acquired Conocophillips's stake in the field
- 2021 - Premier Oil and Chrysaor merge to create Harbour Energy
Geology
Links
- UK Oil and Gas Fields by Approval Date
- List Of Oil and Gas Production Platforms In The UK
- KWSubsea Subsea References
- FoundOcean Subsea References
- Micoperi Offshore Pipeline References
- Global Maritime Pipeline References
- Venture Announces DTI Approval of Mimas Field Development
- ConocoPhillips Completes $2.7 Billion Sale of United Kingdom E&P Subsidiaries
- Harbour Energy to be admitted to trading