=== Summary Information === | === Summary Information === | ||
− | * Ownership: | + | * Ownership: Jawa Satu Regas (JSR) Pertamina, Marubeni and Sojitz |
− | * Website: | + | * Website: https://pertamina.com/ |
* Location: Cilamaya, West Java province, Java Island, Indonesia | * Location: Cilamaya, West Java province, Java Island, Indonesia | ||
− | * Capacity: million tons/annum | + | * Capacity: 2.4 million tons/annum |
− | * Status: | + | * Status: Commissioning 2021 |
=== Brief Description === | === Brief Description === |
Latest revision as of 16:59, 16 March 2021
Contents
Summary Information
- Ownership: Jawa Satu Regas (JSR) Pertamina, Marubeni and Sojitz
- Website: https://pertamina.com/
- Location: Cilamaya, West Java province, Java Island, Indonesia
- Capacity: 2.4 million tons/annum
- Status: Commissioning 2021
Brief Description
- The project entails the construction, operation, and maintenance of a 1,760-megawatt (MW) load-following, combined-cycle, gas turbine (CCGT) power plant and associated facilities.
- Gas is to be supplied by the Jawa Satu FSRU
- The FSRU will be placed 14km offshore in the Cilamaya Sea, east of Jakarta and connected to the power plant via a pipeline about 21km long.
Technical Details
- Storage capacity: 170,000 M3
- Unloading capacity:
- Send out capacity: 300 MMscfd
- Constructor: Samsung Engineering made the vessel conversion
- Licensor:
Ongoing Projects/Project Status
Suppliers / Customers
- Suppliers: LNG is to be supplied from BP’s Tangguh LNG Terminal in West Papua
- Customers: The terminal will supply a new power plant
History
- 2018 - The Asian development bank approved two loans totalling USD 370 million for the project
Other Information
-