Jawa-1 LNG Terminal

From A Barrel Full
Jump to navigation Jump to search

Summary Information

  • Ownership: Jawa Satu Regas (JSR) Pertamina, Marubeni and Sojitz
  • Website: https://pertamina.com/
  • Location: Cilamaya, West Java province, Java Island, Indonesia
  • Capacity: 2.4 million tons/annum
  • Status: Commissioning 2021

Brief Description

  • The project entails the construction, operation, and maintenance of a 1,760-megawatt (MW) load-following, combined-cycle, gas turbine (CCGT) power plant and associated facilities.
  • Gas is to be supplied by the Jawa Satu FSRU
  • The FSRU will be placed 14km offshore in the Cilamaya Sea, east of Jakarta and connected to the power plant via a pipeline about 21km long.

Technical Details

  • Storage capacity: 170,000 M3
  • Unloading capacity:
  • Send out capacity: 300 MMscfd
  • Constructor: Samsung Engineering made the vessel conversion
  • Licensor:

Ongoing Projects/Project Status

Suppliers / Customers

  • Suppliers: LNG is to be supplied from BP’s Tangguh LNG Terminal in West Papua
  • Customers: The terminal will supply a new power plant

History

  • 2018 - The Asian development bank approved two loans totalling USD 370 million for the project

Other Information

-

Links

  1. Asian Development Bank
  2. MOL to Participate in Construction, Ownership, Operation of FSRU for Jawa 1 Gas-Fired IPP Project in Indonesia