Difference between revisions of "Driftwood LNG Export Terminal Project"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
Line 21: | Line 21: | ||
=== Suppliers / Customers === | === Suppliers / Customers === | ||
− | * Suppliers: | + | * Suppliers: The Driftwood Pipeline will have interconnects with the [[ANR Pipeline Company]], [[Tennessee Gas Pipeline]], |
* Customers: | * Customers: | ||
** Vitol - 3mtpa | ** Vitol - 3mtpa |
Revision as of 10:57, 3 February 2022
Contents
Summary Information
- Ownership: Tellurian
- Website: https://www.tellurianinc.com/
- Location: Calcasieu River, south of Lake Charles, Louisiana
- Capacity: 27 million tons/annum
- Status: Planned
Brief Description
- The LNG Facility, includes five LNG plant facilities to liquefy natural gas, three tanks to store the LNG, LNG carrier loading/berthing facilities (Marine Facility), and other utilities
- Construction and operation of about 96 miles of pipeline, three new compressor stations, and 15 new meter stations.
Technical Details
- Storage capacity:
- Constructor:
- Bechtel: lump-sum turn key engineering, procurement and construction contract
- Licensor:
Ongoing Projects/Project Status
- Construction has not yet begun and commissioning is expected in 2025
Suppliers / Customers
- Suppliers: The Driftwood Pipeline will have interconnects with the ANR Pipeline Company, Tennessee Gas Pipeline,
- Customers:
- Vitol - 3mtpa
- Gunvor - 3mtpa
History
- 2017 - Bechtel awarded construction contracts
- 2019 - The final environmental impact assessment was completed
- 2021 - Tellurian signed sales contracts with Gunvor and Vitol
Other Information
- -