=== Summary Information ===
 
=== Summary Information ===
  
* Ownership:  
+
* Ownership: Tellurian
* Website:  
+
* Website: https://www.tellurianinc.com/
* Location:
+
* Location: Calcasieu River, south of Lake Charles, Louisiana
* Capacity: million tons/annum  
+
* Capacity: 27 million tons/annum  
* Status: (In Operation / Planned / Under Construction)
+
* Status: Planned
  
 
=== Brief Description ===
 
=== Brief Description ===
* -
+
* The LNG Facility, includes five LNG plant facilities to liquefy natural gas, three tanks to store the LNG, LNG carrier loading/berthing facilities (Marine Facility), and other utilities
 +
* Construction and operation of about 96 miles of pipeline, three new compressor stations, and 15 new meter stations.
  
 
=== Technical Details ===
 
=== Technical Details ===
 
* Storage capacity:
 
* Storage capacity:
* Constructor:
+
* Constructor:  
 +
** Bechtel: lump-sum turn key engineering, procurement and construction contract
 
* Licensor:
 
* Licensor:
  
 
=== Ongoing Projects/Project Status ===
 
=== Ongoing Projects/Project Status ===
* Commissioning is expected in [[LNG Terminals to be Completed in 202X | 202X]]
+
* Construction has begun in 2022 and commissioning is expected in [[LNG Terminal Projects to be Completed in 2025 | 2025]]
  
 
=== Suppliers / Customers ===
 
=== Suppliers / Customers ===
* Suppliers:  
+
* Suppliers: The Driftwood Pipeline will have interconnects with the [[ANR Pipeline Company]], Cameron Pipeline, Creole Trail Pipeline, [[Tennessee Gas Pipeline]], [[Texas Eastern Transmission Gas Pipeline]] and [[Trunkline Gas Company Pipeline]]
* Customers:  
+
* Customers:
 +
** Vitol - 3mtpa
 +
** Gunvor - 3mtpa
 +
** Total - 2.5mtpa
  
 
=== History ===
 
=== History ===
* -
+
* 2017 - Bechtel awarded construction contracts
 +
* 2019 - The final environmental impact assessment was completed
 +
* 2019 - Total becomes a shareholder and signs gas purchase agreements
 +
* 2021 - Tellurian signed sales contracts with Gunvor and Vitol
 +
* 2022 - Construction of the facility started
  
 
=== Other Information ===
 
=== Other Information ===
Line 29: Line 38:
  
 
=== Links ===
 
=== Links ===
 +
# [https://abarrelfull.blogspot.com/2022/02/bechtel-to-deliver-276-mtpa-driftwood.html Bechtel to Deliver 27.6 MTPA Driftwood LNG Project for Tellurian]
 +
# [https://abarrelfull.blogspot.com/2022/02/total-further-commits-to-tellurian-led.html Total further commits to Tellurian-led Driftwood LNG project through 2.5 Mtpa of LNG offtake and equity investments]
 +
# [https://abarrelfull.blogspot.com/2022/02/final-environmental-impact-statement.html Final Environmental Impact Statement- Driftwood LNG, LLC and Driftwood Pipeline, LLC, collectively Driftwood]
 
# [https://lng-news.blogspot.com/2021/06/tellurian-and-vitol-sign-10-year-lng.html Tellurian and Gunvor sign 10-year LNG agreement for 3 mtpa]
 
# [https://lng-news.blogspot.com/2021/06/tellurian-and-vitol-sign-10-year-lng.html Tellurian and Gunvor sign 10-year LNG agreement for 3 mtpa]
 +
# [https://lng-news.blogspot.com/2021/06/tellurian-and-vitol-sign-10-year-lng_4.html Tellurian and Vitol sign 10-year LNG agreement for 3 mtpa]
 +
# [https://lng-news.blogspot.com/2022/03/tellurians-driftwood-lng-begins.html Tellurian’s Driftwood LNG Begins Construction]
 +
 +
[[category:LNG]]
 +
[[category:USA]]

Latest revision as of 14:40, 28 March 2022

Summary Information

  • Ownership: Tellurian
  • Website: https://www.tellurianinc.com/
  • Location: Calcasieu River, south of Lake Charles, Louisiana
  • Capacity: 27 million tons/annum
  • Status: Planned

Brief Description

  • The LNG Facility, includes five LNG plant facilities to liquefy natural gas, three tanks to store the LNG, LNG carrier loading/berthing facilities (Marine Facility), and other utilities
  • Construction and operation of about 96 miles of pipeline, three new compressor stations, and 15 new meter stations.

Technical Details

  • Storage capacity:
  • Constructor:
    • Bechtel: lump-sum turn key engineering, procurement and construction contract
  • Licensor:

Ongoing Projects/Project Status

  • Construction has begun in 2022 and commissioning is expected in 2025

Suppliers / Customers

History

  • 2017 - Bechtel awarded construction contracts
  • 2019 - The final environmental impact assessment was completed
  • 2019 - Total becomes a shareholder and signs gas purchase agreements
  • 2021 - Tellurian signed sales contracts with Gunvor and Vitol
  • 2022 - Construction of the facility started

Other Information

  • -

Links

  1. Bechtel to Deliver 27.6 MTPA Driftwood LNG Project for Tellurian
  2. Total further commits to Tellurian-led Driftwood LNG project through 2.5 Mtpa of LNG offtake and equity investments
  3. Final Environmental Impact Statement- Driftwood LNG, LLC and Driftwood Pipeline, LLC, collectively Driftwood
  4. Tellurian and Gunvor sign 10-year LNG agreement for 3 mtpa
  5. Tellurian and Vitol sign 10-year LNG agreement for 3 mtpa
  6. Tellurian’s Driftwood LNG Begins Construction