* The development consists of four fields, Cravo, Lirio, Orquidea and Violeta | * The development consists of four fields, Cravo, Lirio, Orquidea and Violeta | ||
* These fields are located in Block 17 offshore Angola in water depths of 1,100 to 1,400 m | * These fields are located in Block 17 offshore Angola in water depths of 1,100 to 1,400 m | ||
− | * The project comprises 34 wells and 8 manifolds connected by 180 km of subsea pipelines to the | + | * The project comprises 34 wells and 8 manifolds connected by 180 km of subsea pipelines to the [[Clov FPSO]] unit |
− | * The gas produced on CLOV will be exported via a subsea line to the onshore | + | * The gas produced on CLOV will be exported via a subsea line to the onshore [[Angola Soyo LNG Terminal]] liquefaction plant |
+ | * '''Begonia''' The Begonia Project will collect oil and gas from the reservoir, via a subsea-to-subsea tie-back to the existing FPSO | ||
=== Contractors === | === Contractors === | ||
Line 28: | Line 29: | ||
* **JDR Cable Systems:** Design, manufacture and testing of 9 umbilical and reeler systems | * **JDR Cable Systems:** Design, manufacture and testing of 9 umbilical and reeler systems | ||
* **KWsubsea:** Lateral buckling and pipeline walking assessment and mitigation design for pipeline systems | * **KWsubsea:** Lateral buckling and pipeline walking assessment and mitigation design for pipeline systems | ||
+ | |||
+ | ==== Begonia ==== | ||
+ | * McDermott: Engineering, procurement, supply, construction, installation, pre-commissioning and assistance to commissioning and start-up (EPSCI) | ||
=== History === | === History === | ||
Line 36: | Line 40: | ||
* 2014 - CLOV begins production | * 2014 - CLOV begins production | ||
* 2021 - Phase 2 begins production | * 2021 - Phase 2 begins production | ||
+ | * 2022 - FID for Begonia project | ||
=== Geology === | === Geology === | ||
Line 54: | Line 59: | ||
# [http://killajoules.wikidot.com/blog:5617 Inauguration of CLOV in Angola] | # [http://killajoules.wikidot.com/blog:5617 Inauguration of CLOV in Angola] | ||
# [https://a-barrel-full.blogspot.com/2021/12/start-up-of-clov-phase-2-project.html Start-up of CLOV Phase 2 project] | # [https://a-barrel-full.blogspot.com/2021/12/start-up-of-clov-phase-2-project.html Start-up of CLOV Phase 2 project] | ||
+ | # [https://a-barrel-full.blogspot.com/2022/09/mcdermott-selected-for-begonia-project.html McDermott Selected for Begonia Project by TotalEnergies EP Angola Block] | ||
Latest revision as of 13:34, 24 September 2022
Contents
Summary Information
- Operator: Total
- Country: Angola
- Location: Block 17
- Production start: 2014
- Partners: Total - 40%, Statoil (23.33%), Esso (Block 17) Limited (20%) and BP (16.67%).
- Type: Oil & Gas
- Estimated Reserves: The proved and probable reserves are estimated at approximately 500 million barrels of oil
- Production Volume:
Description
- The development consists of four fields, Cravo, Lirio, Orquidea and Violeta
- These fields are located in Block 17 offshore Angola in water depths of 1,100 to 1,400 m
- The project comprises 34 wells and 8 manifolds connected by 180 km of subsea pipelines to the Clov FPSO unit
- The gas produced on CLOV will be exported via a subsea line to the onshore Angola Soyo LNG Terminal liquefaction plant
- Begonia The Begonia Project will collect oil and gas from the reservoir, via a subsea-to-subsea tie-back to the existing FPSO
Contractors
Phase 1
- Daewoo Shipbuilding & Marine Eng. Co. Ltd. (DSME): Engineering, procurement, installation and construction of FPSO
- **KBR:** Detailed design of topsides
- **Technip:** 76 kilometers of dynamic and static production and water injection umbilicals
- **Subsea 7:** Engineering, procurement, fabrication and installation of 130km of pipes
- **FMC Technologies:**
- Fabrication, assembly and testing of 36 wellhead systems and 19 subsea trees
- Manufacture of 7 complete manifold systems
- Critical equipment testing, offshore installation support and equipment refurbishment
- **Vallourec:** Supply of 28,500 tons - or 200 km - of coated seamless line pipes and bends
- **JDR Cable Systems:** Design, manufacture and testing of 9 umbilical and reeler systems
- **KWsubsea:** Lateral buckling and pipeline walking assessment and mitigation design for pipeline systems
Begonia
- McDermott: Engineering, procurement, supply, construction, installation, pre-commissioning and assistance to commissioning and start-up (EPSCI)
History
- 2010 - FMC awarded subsea production equipment contract
- 2010 - KBR awarded topsides contract
- 2011 - Technip awarded umbilical contracts
- 2013 - The FPSO arrived in Angola
- 2014 - CLOV begins production
- 2021 - Phase 2 begins production
- 2022 - FID for Begonia project
Geology
- The development will produce two types of oil: one with a 32 to 35° API gravity from the Oligocene reservoirs (Cravo-Lirio) and the other, more viscous, with a 20 to 30° API gravity from the Miocene reservoirs (Orquidea-Violeta)
Links
- Saipem Africa Pipeline References
- Serimax Pipeline References
- KWsubsea Deepwater Project Highlights References
- Acergy S.A. awarded $1.3 billion contract for deepwater development offshore West Africa
- Angola: Total Launches CLOV Development on Block 17
- FMC Technologies Awarded $520 Million Order for Total's CLOV Development
- JDR To Supply FMC With (IWOC) Umbilical And Reeler Systems For The CLOV Project
- KBR to Execute Topsides Detailed Design for TOTAL's CLOV FPSO
- Technip awarded umbilical contracts in Angola
- Vallourec provides Total with a wide range of premium offshore solutions off the Angolan coast
- CLOV Start Up In Angola: Total Increases Block 17 Production To 700,000 Barrels Per Day
- Inauguration of CLOV in Angola
- Start-up of CLOV Phase 2 project
- McDermott Selected for Begonia Project by TotalEnergies EP Angola Block