Surmont Oil Sands Project
Revision as of 14:49, 27 April 2023 by Abarrelfull (talk | contribs)
Summary Information
- Operator: Conoco
 - Country: Canada
 - Location: 60 kilometers southeast of Fort McMurray in Alberta
 - Production start:
 - Partners: Conoco - 50%, Total - 50%
 - Type: Oil
 - Estimated Reserves:
 - Production Volume: 150,000
 
Description
- A Steam Assisted Gravity Drainage project
 
Contractors
++++ Surmont Phase 2
- **Bantrel:**
- Front-end engineering activities (FEL-3)
 - Engineering Procurement & Construction
 
 - **Aker Solutions:**
- Slop Oil Treater Package
 - 2 FWKO Vessels c/w insulation; platform; sample box; sample tubing & sample cooler - 13 ID x 60
 - 2 Treater Vessels c/w insulation; platform; sample tubing; sample cooler & sample box 13 ID x 80
 
 
History
- 1997 - The initial Surmont pilot project began
 - 2003 - The joint venture decided to launch the first phase of commercial development
 - 2005 - Total increased its stake to 50%
 - 2007 - Surmont Project Enters Commercial Production
 - 2008 - Bantrel was awarded front-end engineering activities (FEL-3) for Surmont Phase 2
 - 2010 - Bantrel was awarded the EPC phase for Surmont Phase 2
 - 2015 - Surmont 2 started production
 - 2023 - Suncor acquired Total's stake
 
Geology
Links
- Aker Solutions Oil And Gas Processing References
 - IMV Projects Awarded Surmont Development Study by ConocoPhillips Canada
 - Canada : Total increases its share in the Surmont oil sands leases to 50 %
 - Surmont Project Enters Commercial Production
 - ConocoPhillips Surmont Phase 2 Project, Bantrell
 - Canada: Start-up of Surmont 2
 - Suncor Energy to Acquire TotalEnergies' Canadian Operations for $5.5 Billion, Plus Additional Potential Payments up to an Aggregate Maximum of $600 Million