Angostura Gas Field
Revision as of 07:18, 21 November 2022 by Abarrelfull (talk | contribs) (Created page with "=== Summary Information === * Operator: BHP Billiton * Country: Trinidad And Tobago * Location: * Production start: 2005 * Partners: * Type: Oil / Gas * Estimated Reserves:...")
Summary Information
- Operator: BHP Billiton
- Country: Trinidad And Tobago
- Location:
- Production start: 2005
- Partners:
- Type: Oil / Gas
- Estimated Reserves:
- Production Volume:
Description
- Located offshore Trinidad & Tobago, in approximately 30 meters (100 feet) of water
- The facilities consist of a number of offshore wellhead platforms and a central processing platform connected by intra-field pipelines
- The first development phase, which started in January 2005, produces oil from Kairi and Canteen with the associated gas re-injected.
- The second phase consists in producing the gas principally from Aripo.
Contractors
- **McDermott:** Construction of Platform
- **Tofco:** Gas Bridge and Flare
- **Stolt Offshore:** Installation of an offshore platform and installation of pipelines
- **Bluewater:** Design and supply the SPM system, consisting of a square, turret catenary anchor leg mooring (CALM) buoy, the pipeline end manifold (PLEM), submarine and floating hoses
- **ICON Engineering:** FEED study and cost estimates for three wellhead platform topsides
- **EMAS AMC:** Project management, fabrication, construction and installation of 12-inch flowline along with a complete subsea package comprised of control umbilicals and detailed engineering, construction and installation of the pipeline end manifold (PLEM) and inline sled (ILS) for the Angostura phase 3 field development
History
- 2001 - First discovery
- 2003 - Stolt Offshore awarded contract for installation of an offshore platform and installation of pipelines
- 2005 - Phase 1 of the field productions starts
- 2009 - Technip awarded second phase umbilical and flowline contract
- 2011 - Phase 2 of the field productions starts
- 2015 - Phase 3 contracts awarded
Geology
Links
- International Protective Coatings Platform References
- TOFCO Platform References
- Bluewater Calm Buoy Mooring References
- Icon Engineering Platform References
- Elf announces offshore gas discovery on Trinidad and Tobago 2C Block
- Trinidad and Tobago: Start-up of production from Phase 2 of the Greater Angostura gas field
- Technip awarded a contract for the Angostura gas project in the Caribbean Sea
- Stolt Offshore S.A. Awarded Contracts in Trinidad
- BHP Billiton awards SPM buoy system contract to Bluewater
- EMAS AMC awarded Angostura project offshore Trinidad and Tobago