Jacket, Platform Fabrication and Installation
- Jinzhou 9-3 Oil Field
- Riser Prefabrication and Installation of Submarine Pipeline
- CNOOC
- Riser and Jacket Installation of 3# Island Submarine Pipeline Project
- Jidong Nanpu Oil Field
- Jacket Fabrication and Installation 1-2# Island Submarine Pipeline
- Petrochina
- Jacket Fabrication and Installation of Dagang Guanjiapu Oil Field Submarine Pipeline Project
- Liaohe Oil Field
- Riser and Jacket Installation
- 8 Kuai Submarine Pipeline Laying Project
+++ Offshore Lifting and Facilities Installation achievement
- Suizhong 36-1 Oil Field
- SZ36-1 Transformer Lifting Project
+++ E/I Installation and Commissioning achievement
- Hai Yang Shi You 112 FPSO
- CFD1-1FPSO
- Cable Laying of Communication System, Equipment Installation and Commissioning of Top Module
- 2004.12-2005.7
- COOEC
- 75000T-3# Oil Tanker Living Quarter I/E Construction, Equipment Installation, Cable Laying and System Commissioning. 2005.10-2006.2
DSIC
- FPSO300000t/year FPSO I/E Design, Installation and Commissioning 2005.11-2007.5
CONCCO PHILLPS
- 75000T-6# Oil Tanker Living Quarter I/E Construction, Equipment Installation, Cable Laying and System Commissioning. 2006.3-2006.6
DSIC
- Wenchang FPSO Cable Laying of Communication System, Equipment Installation and Commissioning 2006.11-2007.10
CONCCO PHILLPS