Difference between revisions of "Pegaga Gas Field"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
Line 1: | Line 1: | ||
=== Summary Information === | === Summary Information === | ||
− | * Operator: | + | * Operator: Mubadala |
− | * Country: | + | * Country: Malaysia |
− | * Location: | + | * Location: Block 320 offshore |
− | * Production start: | + | * Production start: 2022 |
− | * Partners: | + | * Partners: Mubadala, Petronas, Shell |
* Type: Oil / Gas | * Type: Oil / Gas | ||
* Estimated Reserves: | * Estimated Reserves: | ||
Line 11: | Line 11: | ||
=== Description === | === Description === | ||
* The development concept comprises of an Integrated Central Processing Platform (ICPP) consisting of an 8-legged jacket. | * The development concept comprises of an Integrated Central Processing Platform (ICPP) consisting of an 8-legged jacket. | ||
− | The facility is designed for gas throughput of 550 million standard cubic feet of gas per day plus condensate. | + | * The facility is designed for gas throughput of 550 million standard cubic feet of gas per day plus condensate. |
− | The produced fluids are evacuated through a new 38 inch subsea pipeline tying into an existing offshore network and subsequently to the onshore [[Malaysia LNG Terminal| Malaysia LNG plant in Bintulu]]. | + | * The produced fluids are evacuated through a new 38 inch subsea pipeline tying into an existing offshore network and subsequently to the onshore [[Malaysia LNG Terminal| Malaysia LNG plant in Bintulu]]. |
=== Contractors === | === Contractors === | ||
− | * | + | * Sapura Fabrication: Engineering, Procurement, Construction, Installation & Commissioning (EPCIC) |
=== History === | === History === |
Revision as of 08:25, 22 March 2023
Summary Information
- Operator: Mubadala
- Country: Malaysia
- Location: Block 320 offshore
- Production start: 2022
- Partners: Mubadala, Petronas, Shell
- Type: Oil / Gas
- Estimated Reserves:
- Production Volume:
Description
- The development concept comprises of an Integrated Central Processing Platform (ICPP) consisting of an 8-legged jacket.
- The facility is designed for gas throughput of 550 million standard cubic feet of gas per day plus condensate.
- The produced fluids are evacuated through a new 38 inch subsea pipeline tying into an existing offshore network and subsequently to the onshore Malaysia LNG plant in Bintulu.
Contractors
- Sapura Fabrication: Engineering, Procurement, Construction, Installation & Commissioning (EPCIC)
History
- 2018 - Final investment decision taken