Difference between revisions of "Judy, Joanne and Jade Gas and Condensate Fields"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) (Created page with "Summary Information * Operator: Conocophillips * Country: UK * Location: central North Sea * Production start: * Partners: * Type: Oil / Gas * Estimated Reserves: * Produc...") |
Abarrelfull (talk | contribs) |
||
Line 1: | Line 1: | ||
− | Summary Information | + | === Summary Information === |
* Operator: Conocophillips | * Operator: Conocophillips | ||
* Country: UK | * Country: UK | ||
Line 9: | Line 9: | ||
* Production Volume: | * Production Volume: | ||
− | + | === Description === | |
− | * | + | * Judy and Joanne are in Block 30/7a of the UK central North Sea approximately 240-kilometres south-east of Aberdeen. They sit in Quadrant 30 of the J-Area (or J-Block) with overlapping reservoirs. |
− | * The Joanne field is a sub-sea development tied back to the manned Judy platform | + | ** Judy is a manned platform with accommodation, production, processing and gas injection equipment. |
+ | ** Joanne is a subsea manifold with six subsea wells tied back to Judy through two 5.5 kilometre pipelines. | ||
+ | * Jade lies approximately 240-kilometres south east of Aberdeen in Block 30/2c. It is a high-pressure/high-temperature (HP/HT) development, which consists of a normally unmanned installation (NUI) tied back via a subsea pipeline to the Judy facility from where all operations are controlled | ||
+ | |||
+ | * The Joanne field is a sub-sea development tied back to the manned Judy platform . The Judy/Joanne fields currently produce from 16 wells. | ||
* Jade was developed using a normally unmanned wellhead platform and currently produces from eight wells. Production from Jade is exported via a sub-sea pipeline to the Judy platform where it is commingled and processed with Judy and Joanne production. | * Jade was developed using a normally unmanned wellhead platform and currently produces from eight wells. Production from Jade is exported via a sub-sea pipeline to the Judy platform where it is commingled and processed with Judy and Joanne production. | ||
− | * Gas processed on the Judy platform is transported through the | + | * Gas processed on the Judy platform is transported through the [[CATS Central Area Transmission System Gas Pipeline]] to the [[Teesside Gas Processing Plant TGPP]] and liquids are transported to Teesside through the Norpipe system. |
− | + | === Contractors === | |
* **Consorzio Ital Offshore:** Judy Wellhead Platform consrtuction | * **Consorzio Ital Offshore:** Judy Wellhead Platform consrtuction | ||
* **Saipem:** "J" Block Judy Wellhead Platform - T&I | * **Saipem:** "J" Block Judy Wellhead Platform - T&I | ||
Line 23: | Line 27: | ||
* **FoundOcean:** Grouting for Platform & Subsea Structures | * **FoundOcean:** Grouting for Platform & Subsea Structures | ||
− | + | === Jade === | |
* **Heerema:** Platform construction | * **Heerema:** Platform construction | ||
* **Saipem:** Installation of the Jade Platform & pipelines | * **Saipem:** Installation of the Jade Platform & pipelines | ||
Line 31: | Line 35: | ||
* **Nessco:** Communication systems | * **Nessco:** Communication systems | ||
− | + | === History === | |
* 1993 - Judy & Joanne field development approved | * 1993 - Judy & Joanne field development approved | ||
+ | * 1995 - Jade field discovered | ||
* 2000 - Jade development given government approval | * 2000 - Jade development given government approval | ||
* 2002 - Production started at Jade | * 2002 - Production started at Jade | ||
* 2017 - Chrysaor acquired Shell's stake in the field. | * 2017 - Chrysaor acquired Shell's stake in the field. | ||
− | + | === Geology === | |
* | * | ||
Revision as of 18:44, 30 November 2021
Summary Information
- Operator: Conocophillips
- Country: UK
- Location: central North Sea
- Production start:
- Partners:
- Type: Oil / Gas
- Estimated Reserves:
- Production Volume:
Description
- Judy and Joanne are in Block 30/7a of the UK central North Sea approximately 240-kilometres south-east of Aberdeen. They sit in Quadrant 30 of the J-Area (or J-Block) with overlapping reservoirs.
- Judy is a manned platform with accommodation, production, processing and gas injection equipment.
- Joanne is a subsea manifold with six subsea wells tied back to Judy through two 5.5 kilometre pipelines.
- Jade lies approximately 240-kilometres south east of Aberdeen in Block 30/2c. It is a high-pressure/high-temperature (HP/HT) development, which consists of a normally unmanned installation (NUI) tied back via a subsea pipeline to the Judy facility from where all operations are controlled
- The Joanne field is a sub-sea development tied back to the manned Judy platform . The Judy/Joanne fields currently produce from 16 wells.
- Jade was developed using a normally unmanned wellhead platform and currently produces from eight wells. Production from Jade is exported via a sub-sea pipeline to the Judy platform where it is commingled and processed with Judy and Joanne production.
- Gas processed on the Judy platform is transported through the CATS Central Area Transmission System Gas Pipeline to the Teesside Gas Processing Plant TGPP and liquids are transported to Teesside through the Norpipe system.
Contractors
- **Consorzio Ital Offshore:** Judy Wellhead Platform consrtuction
- **Saipem:** "J" Block Judy Wellhead Platform - T&I
- **BiFab:** EPC contract for Judy Accommodation Unit
- **FoundOcean:** Grouting for Platform & Subsea Structures
Jade
- **Heerema:** Platform construction
- **Saipem:** Installation of the Jade Platform & pipelines
- **J P Kenny:** Detail design and review of vendor data for CRA cladding of 16 inch tie-in spool
- **FoundOcean:** Grouting for Platform
- **Global Maritime:** Warranty surveyor for conventional pipelay
- **Nessco:** Communication systems
History
- 1993 - Judy & Joanne field development approved
- 1995 - Jade field discovered
- 2000 - Jade development given government approval
- 2002 - Production started at Jade
- 2017 - Chrysaor acquired Shell's stake in the field.
Geology
Links
- BG Group, Databook
- UK Oil and Gas Fields by Approval Date
- List Of Oil Production Platforms In The UK
- Saipem Fixed Offshore Production Facilities Project References
- Saipem Europe Pipeline References
- Bifab Platform References
- FoundOcean Europe Subsea References
- International Protective Coatings Platform References
- J P Kenny Subsea References
- Nessco Platform References
- Global Maritime Pipeline References
- The Jade Field, Offshore Petroleum Production And Pipe-Lines (Assessment Of Environmental Effects) Regulations 1999 Licence P 672 - Licence Having Effect Under The Petroleum Act 1998
- Shell to sell package of UK North Sea assets to Chrysaor for up to $3.8bn