| Line 1: | Line 1: | ||
| − | + | === Summary Information === | |
| − | |||
| − | |||
* Operator: EnQuest | * Operator: EnQuest | ||
* Country: UK | * Country: UK | ||
* Location: North Sea | * Location: North Sea | ||
| − | * Production start: | + | * Production start: 2015 |
* Partners: | * Partners: | ||
| − | * Type: Oil | + | * Type: Oil |
* Estimated Reserves: | * Estimated Reserves: | ||
* Production Volume: | * Production Volume: | ||
| − | + | === Description === | |
| − | * The | + | * The Alma/Galia fields are located in blocks 30/24c and 30/25c respectively, 310km southeast of Aberdeen, in the Central North Sea. |
| − | * | + | * Production is via the EnQuest Producer Floating Production, Storage and Offloading vessel [[Enquest Producer FPSO]] |
| + | * The field were previously called Duncan and Argyll Oil Fields | ||
| − | + | === Contractors === | |
* **Technip:** | * **Technip:** | ||
** Installation of two 10” production flexible flowlines, one 8” water injection flexible flowline and one further 8” production flexible flowline, | ** Installation of two 10” production flexible flowlines, one 8” water injection flexible flowline and one further 8” production flexible flowline, | ||
| Line 25: | Line 24: | ||
* **Jumbo:** FPSO mooring, installation and hook-up contract | * **Jumbo:** FPSO mooring, installation and hook-up contract | ||
| − | + | === History === | |
* 1983 - Duncan field development approved | * 1983 - Duncan field development approved | ||
* 2012 - Field development approval given | * 2012 - Field development approval given | ||
| Line 32: | Line 31: | ||
* 2014 - FPSO mooring spread installed | * 2014 - FPSO mooring spread installed | ||
| − | + | === Geology === | |
* | * | ||
| − | + | === Links === | |
# [[UK Oil and Gas Fields by Approval Date]] | # [[UK Oil and Gas Fields by Approval Date]] | ||
# [http://killajoules.wikidot.com/blog:2690 Technip awarded contract for EnQuest’s Alma and Galia development in UK North Sea] | # [http://killajoules.wikidot.com/blog:2690 Technip awarded contract for EnQuest’s Alma and Galia development in UK North Sea] | ||
# [http://killajoules.wikidot.com/blog:3508 Jumbo main installation contractor for EnQuest Producer] | # [http://killajoules.wikidot.com/blog:3508 Jumbo main installation contractor for EnQuest Producer] | ||
# [http://killajoules.wikidot.com/blog:5112 Jumbo installs North Sea FPSO mooring spread] | # [http://killajoules.wikidot.com/blog:5112 Jumbo installs North Sea FPSO mooring spread] | ||
Revision as of 12:02, 29 May 2024
Summary Information
- Operator: EnQuest
- Country: UK
- Location: North Sea
- Production start: 2015
- Partners:
- Type: Oil
- Estimated Reserves:
- Production Volume:
Description
- The Alma/Galia fields are located in blocks 30/24c and 30/25c respectively, 310km southeast of Aberdeen, in the Central North Sea.
- Production is via the EnQuest Producer Floating Production, Storage and Offloading vessel Enquest Producer FPSO
- The field were previously called Duncan and Argyll Oil Fields
Contractors
- **Technip:**
- Installation of two 10” production flexible flowlines, one 8” water injection flexible flowline and one further 8” production flexible flowline,
- Installation of three 8” flexible risers,
- Installation of two production control umbilicals/risers,
- Installation of four power cables and associated dynamic risers,
- Procurement, fabrication and installation of a 175 ton manifold structure,
- Associated trenching operations, tie-ins, testing and commissioning.
- **Jumbo:** FPSO mooring, installation and hook-up contract
History
- 1983 - Duncan field development approved
- 2012 - Field development approval given
- 2012 - Technip awarded subsea contract
- 2012 - Jumbo awarded FPSO mooring, installation and hook-up contract
- 2014 - FPSO mooring spread installed