Difference between revisions of "Pegaga Gas Field"

From A Barrel Full
Jump to navigation Jump to search
(Created page with "=== Summary Information === * Operator: * Country: * Location: * Production start: * Partners: * Type: Oil / Gas * Estimated Reserves: * Production Volume: === Descrip...")
 
Line 10: Line 10:
  
 
=== Description ===
 
=== Description ===
*  
+
* The development concept comprises of an Integrated Central Processing Platform (ICPP) consisting of an 8-legged jacket.
 +
The facility is designed for gas throughput of 550 million standard cubic feet of gas per day plus condensate.
 +
The produced fluids are evacuated through a new 38 inch subsea pipeline tying into an existing offshore network and subsequently to the onshore [[Malaysia LNG Terminal| Malaysia LNG plant in Bintulu]].
  
 
=== Contractors ===
 
=== Contractors ===
Line 16: Line 18:
  
 
=== History ===
 
=== History ===
*  
+
* 2018 - Final investment decision taken
  
 
=== Geology ===
 
=== Geology ===
Line 22: Line 24:
  
 
=== Links ===
 
=== Links ===
#
+
# [https://abarrelfull.blogspot.com/2023/03/pegaga-gas-development-in-malaysia.html Pegaga Gas Development in Malaysia Approved]
  
  

Revision as of 08:24, 22 March 2023

Summary Information

  • Operator:
  • Country:
  • Location:
  • Production start:
  • Partners:
  • Type: Oil / Gas
  • Estimated Reserves:
  • Production Volume:

Description

  • The development concept comprises of an Integrated Central Processing Platform (ICPP) consisting of an 8-legged jacket.

The facility is designed for gas throughput of 550 million standard cubic feet of gas per day plus condensate. The produced fluids are evacuated through a new 38 inch subsea pipeline tying into an existing offshore network and subsequently to the onshore Malaysia LNG plant in Bintulu.

Contractors

  • -

History

  • 2018 - Final investment decision taken

Geology

Links

  1. Pegaga Gas Development in Malaysia Approved