* Country: UK | * Country: UK | ||
* Location: west of Shetland | * Location: west of Shetland | ||
− | * Production start: | + | * Production start: 2018 |
* Partners: Shell, ConocoPhillips and Chevron | * Partners: Shell, ConocoPhillips and Chevron | ||
* Type: Oil / Gas | * Type: Oil / Gas | ||
Line 11: | Line 11: | ||
+++ Description | +++ Description | ||
* Clair Ridge is a £4.5bn development announced by BP and its coventurers ConocoPhillips, Chevron, and Shell in October 2011. It is an extension of the giant [[Clair Oil Field]] | * Clair Ridge is a £4.5bn development announced by BP and its coventurers ConocoPhillips, Chevron, and Shell in October 2011. It is an extension of the giant [[Clair Oil Field]] | ||
− | * It | + | * Two new, bridge-linked platforms and oil and gas export pipelines were constructed as part of the Clair Ridge project. The new pipes were: |
+ | ** A 5.5-kilometre, 22-inch oil export pipeline tying into the Clair Phase 1 export pipeline. | ||
+ | ** A 14.6-kilometre, six-inch gas export pipeline tying Clair Ridge into the [[West Of Shetlands Gas Pipeline System]] | ||
+ | * It came onstream in 2018 and will produce up to 120,000 barrels of oil per day at peak. | ||
* The Clair Ridge development, is the first sanctioned large-scale offshore enhanced oil recovery (EOR) scheme using reduced salinity water injection (LoSal® EOR). | * The Clair Ridge development, is the first sanctioned large-scale offshore enhanced oil recovery (EOR) scheme using reduced salinity water injection (LoSal® EOR). | ||
* Oil and Gas are to be transported from Clair Ridge to [[Sullom Voe Oil Terminal]] | * Oil and Gas are to be transported from Clair Ridge to [[Sullom Voe Oil Terminal]] | ||
Line 31: | Line 34: | ||
* 2012 - BP announces reduced salinity water injection project | * 2012 - BP announces reduced salinity water injection project | ||
* 2013 - Clair Ridge Jackets Safely Installed | * 2013 - Clair Ridge Jackets Safely Installed | ||
+ | * 2018 - First oil produced | ||
+++ Geology | +++ Geology | ||
Line 46: | Line 50: | ||
# [http://killajoules.wikidot.com/blog:4447 New Clair Ridge Jackets Safely Installed West Of Shetland] | # [http://killajoules.wikidot.com/blog:4447 New Clair Ridge Jackets Safely Installed West Of Shetland] | ||
# [http://killajoules.wikidot.com/blog:5970 Global Marine lands Subsea 7 contract] | # [http://killajoules.wikidot.com/blog:5970 Global Marine lands Subsea 7 contract] | ||
+ | # [https://abarrelfull.blogspot.com/2023/05/bp-starts-up-clair-ridge-production.html | ||
+ | |||
+ | [[category:Field]] | ||
+ | [[category:UK]] | ||
+ | [[category:BP]] |
Revision as of 07:59, 15 May 2023
Summary Information
- Operator: BP
- Country: UK
- Location: west of Shetland
- Production start: 2018
- Partners: Shell, ConocoPhillips and Chevron
- Type: Oil / Gas
- Estimated Reserves: 640 million barrels of recoverable oil
- Production Volume:
+++ Description
- Clair Ridge is a £4.5bn development announced by BP and its coventurers ConocoPhillips, Chevron, and Shell in October 2011. It is an extension of the giant Clair Oil Field
- Two new, bridge-linked platforms and oil and gas export pipelines were constructed as part of the Clair Ridge project. The new pipes were:
- A 5.5-kilometre, 22-inch oil export pipeline tying into the Clair Phase 1 export pipeline.
- A 14.6-kilometre, six-inch gas export pipeline tying Clair Ridge into the West Of Shetlands Gas Pipeline System
- It came onstream in 2018 and will produce up to 120,000 barrels of oil per day at peak.
- The Clair Ridge development, is the first sanctioned large-scale offshore enhanced oil recovery (EOR) scheme using reduced salinity water injection (LoSal® EOR).
- Oil and Gas are to be transported from Clair Ridge to Sullom Voe Oil Terminal
+++ Contractors
- **AMEC:**
- Detailed engineering and project management services for the construction and installation phase of two new bridge linked platforms. This includes detail design, follow-on engineering, site support, plus procurement, supply chain services, materials management and information management services for the whole project
- Hook up and commissioning services (HUC) for the two Clair Ridge platforms
- **Kvaerner:** Drilling & Production Jacket and Piles, Quarters Utility Jacket and Piles
- **Subsea 7:** project management, engineering, procurement, fabrication and installation of a 6km 22” oil export pipeline and a 14km 6” gas export pipeline connected to the new production facilities and existing Clair Phase 1 export systems
- **Hyundai Heavy Industries:** Construction of platform topsides
- **Global Marine:** Submarine fibre optic link between platforms
+++ History
- 2011 - BP Confirms Extension of Giant Clair Field
- 2011 - The Government gave BP and its partners Shell, ConocoPhillips and Chevron consent for the project
- 2011 - AMEC awarded EPMS for the main platform design
- 2012 - Subsea 7 awarded pipeline contract
- 2012 - BP announces reduced salinity water injection project
- 2013 - Clair Ridge Jackets Safely Installed
- 2018 - First oil produced
+++ Geology
+++ Links
- Foundocean Subsea References
- Kvaerner Platform References
- BP Confirms Extension of Giant Clair Field West of Shetland in the UK
- Consent given for £4.5 billion Clair Ridge development
- AMEC awarded £150 million Clair Ridge design engineering, North Sea
- Subsea 7 awarded contract, West of Shetland
- BP Technology Boosts Oil Recovery Adding To Potential Energy Supplies
- AMEC awarded £68 million Clair Ridge hook up contract, North Sea
- New Clair Ridge Jackets Safely Installed West Of Shetland
- Global Marine lands Subsea 7 contract
- [https://abarrelfull.blogspot.com/2023/05/bp-starts-up-clair-ridge-production.html