Summary Information

  • Source: Malin, Oregon, USA
  • Destination: Wadsorth, Nevada, USA
  • Ownership: Tuscarora Gas Transmission Company (Transcanada)
  • Website: http://www.transcanada.com/tuscarora/
  • Length: 491 kilometres (305 miles)
  • Capacity: per day
  • Status Operating

Details

  • The 305-mile (491-km) 20-inch-diameter Tuscarora Gas Transmission System delivers natural gas from the Western Canadian Sedimentary Basin, the Rocky Mountains and other US basins to communities in California and Nevada.
  • Tuscarora extends from an interconnection with TransCanadas Gas Transmission Northwest Corporation System at the Malin Center Natural Gas Hub, Oregon, to its terminus near Wadsworth, Nevada, where it interconnects with Paiute Gas Pipeline.

Contractors

  • UniversalPegasus: Engineering design, preliminary survey, mapping, material procurement, and inspection services

History

  • 1995 - Constructed and placed into service
  • 2000 - Hungry Valley Lateral Completed
  • 2002 - System Expansion Phase I Completed
  • 2006 - TransCanada acquired the pipeline
  • 2008 - Further System Expansion Completed

Other Information

  • -

Links

  1. Pipeline Map
  2. TransCanada, Tuscarora
  3. EIA Natural Gas Pipeline Projects 2000-2009
  4. Universalpegasus Pipeline References
  5. TC PipeLines, LP acquires Tuscarora Gas Transmission Company