Tuban East Java Refinery Project
Jump to navigation
Jump to search
Contents
Summary Information
- Ownership: Rosneft 45% and Pertamina 55%
- Website: http://www.pertamina.com/
- Wiki Page: Tuban East Java Refinery
- Location: Tuban, East Java, Indonesia
- Capacity: 15.0 million tons/annum & 300,000 bbl/day
- Nelson Complexity: 13.1
- Project Stage: Planned
- Expected Completion:
- Budget:
The Project
- Project Type: Green field refinery and petrochemicals plant
- Project Summary: The planned refining capacity is 15 mmpta (300 kbpd) and the targeted capacity of the petrochemical complex is over 1 mmtpa of ethylene and 1.3 mmtpa of aromatics.
- Main Contractors
- Tecnicas Reunidas: Basic Engineering Design (BED) and the Front-End Engineering Design (FEED)
Refining Units
- Atmospheric Distillation
- Sulphur Recovery Plant
- Sour Water Stripping Unit
- Amine Recovery Unit
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
- The feedstock for TGRR will be medium and heavy sulfur crude oil grades
- The crude oil terminal will be able to accommodate VLCCs of up to 300 thousand tonnes.
Products Produced
-
History
- 2005 - Sinopec & Pertamina sign an MOU
- 2012 - Saudi Aramco signed Memorandum of Understanding
- 2017 - Rosneft and Pertamina sign JV agreement
- 2019 - Tecnicas Reunidas selected for FEED
Other Information
-