Sepia Oil Field

From A Barrel Full
Jump to navigation Jump to search

Summary Information

  • Operator: Petrobras
  • Country: Brazil
  • Location: Santos Basin
  • Production start: 2021
  • Partners: PETRONAS (21%), Petrobras (30%), TotalEnergies (28%) and QatarEnergy (21%).
  • Type: Oil / Gas
  • Estimated Reserves:
  • Production Volume: 170,000 bpd (2022)

Description

  • The Sépia Leste field is at approximately 250 km and the Sépia field 185 km from the coast of Rio de Janeiro state, at a depth of 2,165 meters.
  • The permanent development utilises the Carioca FPSO MV30 but an early production system used Cidade de São Vicente FPSO
  • A total of 15 wells are planned, but the first phase includes seven-riser wells (3 producers and 4 injector wells)
  • The P-85 FPSO will be added to the field in 2028 as part of the phase 2 development

Contractors

  • MODEC: Engineering, procurement, construction, mobilization and installation of the FPSO, including topsides processing equipment as well as hull and marine systems.
  • Sofec designed and provided the spread mooring system
  • McDermott Detailed engineering, surveys, supply, installation and pre-commissioning of rigid pipelines, jumpers, buoyance modules, strakes and riser monitoring systems for seven-riser wells (3 producers and 4 injector wells) connected to the Carioca FPSO MV30

Phase 2

  • Seatrium: EPC for FPSO

History

  • 2014 - The Sépia field was declared commercially viable
  • 2015 - The Sépia Leste field was declared commercially viable
  • 2016 - Early production system produces oil for 180 days
  • 2017 - Modec awarded FPSO contract
  • 2021 - First oil produced
  • 2021 - Petronas becomes 21% shareholder and Qatarenergy 14.4% owner
  • 2022 - New oil discovery made in the field
  • 2024 - FID for second phase development

Geology

  • The field is located in the pre-salt

Links

  1. Declaration of the Commercial Viability of the Sépia Leste area, in the pre-salt layer of the Santos Basin
  2. Early Production System starts up in the Santos Basin's Sepia pre-salt
  3. Contracting of FPSO for Sepia field
  4. McDermott Awarded EPCI Contract by Petrobras for Sepia Field Project
  5. MODEC’s FPSO Carioca MV30 achieves First Oil and starts 21-Year Time Charter
  6. PETRONAS Wins Sépia Field In Brazil Bid Round
  7. Qatarenergy announces hydrocarbon discovery in Brazil’s Sépia field
  8. Brazil: TotalEnergies expands its pre-salt footprint on giant low-cost and low emissions reserves
  9. Petrobras on P-84 and P-85 contracting process
  10. Qatarenergy Announces FID In the Second Development Phase For Brazil’s Sépia Field