Nizhnekamsk Refinery Upgrade Project
Jump to navigation
Jump to search
Contents
Summary Information
- Ownership: OAO Nizhnekamskneftekhim (TAIF-NK)
- Website: https://en.taifnk.ru/
- Wiki Page: Nizhnekamsk Refinery
- Location: Nizhnekamsk, Tatarstan, Russia
- Capacity: 7.0 million tons/annum & 140,000 bbl/day
- Nelson Complexity:
- Project Stage: Basic engineering awarded
- Expected Completion: 2015
- Budget:
The Project
- Project Type: Residuum Upgrading
- Project Summary: A VCC-based Deep Conversion Complex is being constructed. The complex will process 2.7 million tons per annum of refinery vacuum residues, and 1.6 million tons per annum of distillates into high value petrochemical feedstocks and Euro 5 diesel.
- Main Contractors
- KBR: VCC License and Basic Engineering Package
- Toyo Engineering: Detailed engineering and procurement
Refining Units
- Veba Catalytic Cracker - VCC
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
- The complex will be fed with vacuum residues from the Nizhnekamsk Refinery
Products Produced
- Petrochemical feedstocks and Euro 5 diesel
History
- 2012 - KBR awarded licence and basic engineering contract for upgrade project
- 2013 - Toyo Engineering awarded detailed engineering and procurement contract
Other Information
-