Summary Information
- Ownership: Nippon Oil
- Website: http://www.noe.jx-group.co.jp/english/
- List of Nippon Oil Refineries
- Location: Yokahama, Japan
- Capacity: 13.5 million tons/annum & 270,000 bbl/day
- Nelson Complexity:
- Refining Depth:
Brief Description
- A large high complexity refinery
Refining Units
- Atmospheric Distillation
- Vacuum Crude Oil Distillation - 130,000
- Residue Fluid Catalytic Cracking (RFCC) unit 40,000 bpd
- Catalytic Cracking - 83,000
- Alkylation - 9.000
- Catalytic Reforming - 50.000 + 14.000
- Desulfurisation
- Naphtha - 71.500
- FCC Gasoline - 28.000
- Middle Distillate - 137.500
- Coker 20,000 bpd (idled)
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
- -
Products Produced
- -
Ongoing Projects
- The capacity of the refinery is being decreased with the closure of a 70,000 bpd distillation column in October 2010
Other Information
- -
History
- 1968 - Solvent Extraction Unit added
- 1983 - Visbreaker unit commissioned
- 1986 - Catalytic Reforming & Naphtha Desulphurisation Units started
- 1993 - Residuum Hydrodesulfurization Unit & Sulphur units commissioned
- 2009 - Construction Completed for Japan’s first bio-ETBE Production Plant
- 2010 - A 70,000 bpd distilation column was decommissioned
Relevant Links
- Chiyoda Visbreaking Units
- Chiyoda Catalytic Reforming Units
- Chiyoda Lubricating Oil Refining Units
- Chiyoda Naphtha And Middle Distillate Hydrodesulfurization U
- Chiyoda Residuum Hydrodesulfurization Units
- Chiyoda H2S Removal Units With Amine
- Chiyoda Sour Water Stripping Units
- Chiyoda Claus Tail Gas Treating Units
- Chiyoda Vacuum Flasher Vacuum Distillation Units
- Japan's JX considers closing Negishi refinery
- Japan's JX, Fuji Oil scrap CDUs
- Construction Completed for Japan’s first bio-ETBE Production Plant at Negishi Refinery