  • The plant has a capacity of 1.5 billion cubic feet per day (Bcf/d) of natural gas and is capable of extracting up to 70,000 barrels per day (BPD) of natural gas liquids (NGLs).
  • The plant processes natural gas produced in the Piceance Basin
  • Natural gas liquids are transported on the Mid America NGL Pipeline System and the Chaparral NGL Pipeline
  • Gas is transported on the Questar Pipeline Company

Related Oil and Gas Fields

  • The plant processes gas produced in fields of the Piceance Basin

Ongoing Projects

  • -

Other Information

  • -

History

  • 2007 - Phase I entered production
  • 2009 - Phase II is commissioned