Hrvatska LNG Terminal
Jump to navigation
Jump to search
Contents
Summary Information
- Ownership: LNG Hrvatska
- Website: http://www.lng.hr/en/
- Location: Island of Krk
- Capacity: 2.6 BCM/annum
- Status: Under construction
Brief Description
- The LNG receiving terminal will be located in Omišalj county on the Island of Krk in Croatia, North Adriatic
- It consists of the FSRU, Golar Viking and onshore facilities
- It is connected to the Croatian gas transmission system by the Omišalj-Zlobin gas pipeline
Technical Details
- Storage capacity: Tank capacity (full containment): 2x180.000 m³
- Unloading capacity: Size of LNG supply ships: 75,000 - 265,000 m³
- Send out capacity:
- Constructor:
- Golar LNG: Supply of FSRU
- Consortium Pomgrad, GP Krk and STSI: engineering, procurement and construction of jetty with the auxiliary facilities and connecting high-pressure gas pipeline for the receiving LNG terminal
- Expansion: Wärtsilä provided engineering and CIMCSOE manufactured the module
Ongoing Projects/Project Status
- The terminal was commissioned in 2021
- An extra regasification module is being added to increase capacity.
Suppliers / Customers
- Suppliers:
- Customers:
History
- 2015 - Project awarded strategic status by the Croatian Government
- 2019 - Golar LNG awarded contract for FSRU
- 2019 - EU awards aid to the project
- 2021 - Terminal begins commercial operations
- 2023 - Expansion project launched
Other Information
-
Links
- Declaration For Cooperation Between Gaz-System S.A. And The Croatian Gas Transmission System Operator Plinacro D.O.O.
- LNG Hrvatska awards Golar LNG contract for FSRU
- State aid: Commission approves public support for Croatian LNG terminal at Krk island
- NOTICE ON ADOPTION OF FINAL INVESTMENT DECISION
- First Croatian LNG terminal officially inaugurated in Krk island
- Wärtsilä to extend regasification capacity for Croatian LNG terminal
- CIMC SOE wins regasification module order