+++ Description
- The GWF Phase 1 Project will develop the Goodwyn GH and Tidepole fields, via a subsea tie-back to the existing [[[Goodwyn A Gas And Condensate Field | Goodwyn A platform]]]
- GWF-2 will develop the hydrocarbon resources of the Keast, Dockrell, Sculptor, Rankin, Lady Nora and Pemberton fields
- The gas is to supply [[[North West Shelf LNG]]]
+++ Contractors
++++ Phase I
- **Technip:** Load out, transportation and installation of 16 kilometers of 16” gas flow line from the Tidepole manifold to the GWA platform
- **FMC Technologies:** Design, manufacture and supply of subsea production systems
- **Aker Solutions:** Project management, design, engineering, manufacturing and verification testing of two steel tube umbilicals
++++ Phase II
- **Wood Group Kenny (WGK):**
* Front end engineering design (FEED) of the flowline system, and associated procurement support * Flowline system detailed design and support the related procurement and construction processes
- **FMC Technologies:** subsea production trees, wellheads, manifolds, subsea and topside controls, and flowline connection systems.
+++ History
- 2011 - Greater Western Flank Phase 1 Project approved
- 2012 - Equipment and installation contracts awarded
- 2015 - FEED awarded for phase II
+++ Geology
+++ Links
- [[[Serimax Pipeline References]]]
- NWS Project Approves Greater Western Flank Phase 1 Project
- FMC Technologies Awarded $150 Million Subsea Systems Contract for Greater Western Flank Phase 1 Project
- Technip awarded subsea installation contract in Australia
- Aker Solutions secures umbilical contract in Australia
- Wood Group Kenny awarded FEED contract on Woodside’s proposed Greater Western Flank Phase 2 development
- FMC Technologies Awarded $180 Million Subsea Systems Contract on Australian Project from Woodside
- Wood Group wins further design contract for GWF-2
- TechnipFMC Awarded Significant Integrated EPCI (iEPCI™) Contract for Woodside’s Lambert Deep and Greater Western Flank Fields in Australia