EIA Liquids Pipeline Projects 2015-2020

From A Barrel Full
Jump to navigation Jump to search
  1. Sand Hills NGL Pipeline
    • DCP Midstream; Enbridge; Phillips 66
    • Expansion - Completed - Q2 - 2015
    • 180 miles, 20 inches
    • NGLs
    • 50,000 bpd
    • Capacity increased from 200,000 b/d to 250,000 b/d "by managing hydraulics and pressure flows in the pipeline". New laterals to Red Bluff Lake and Lea County (both in Texas).
  2. Southern Access Crude Oil Pipeline
    • Enbridge
    • Expansion - Completed - Q2 - 2015
    • 454 miles, 42 inches
    • Crude
    • 240,000 bpd
    • Capacity increased from 560,000 b/d to 800,000 b/d.
  3. Alberta Clipper Pipeline (Line 67)
    • Enbridge
    • Expansion - Completed - Q3 - 2015 (pump upgrade phase 2—Canada)
    • 786 miles, 36 inches
    • Crude
    • 230,000 bpd
    • Line 67 goes from Alberta, Canada to Wisconsin. Upgrading of pumps brought Canadian capacity up from 570,000 b/d to 800,000 b/d (north of the 3-mile segment in North Dakota that connects the U.S. and Canadian pipeline). Capacity is based on heavy crude; the total capacity can be almost 890,000 b/d if the pipeline is carrying light crude.
  4. Alberta Clipper Pipeline (Line 67)
    • Enbridge
    • Expansion - Completed - Q3 - 2015 (pump upgrade phase 2—USA)
    • 323 miles, 36 inches
    • Crude
    • 230,000 bpd
    • Line 67 goes from Alberta, Canada to Wisconsin. Upgrading of pumps brought U.S. capacity up from 570,000 b/d to 800,000 b/d (south of the 3-mile segment in North Dakota that connects the U.S. and Canadian pipeline). Capacity is based on heavy crude; the total capacity can be almost 890,000 b/d if the pipeline is carrying light crude.
  5. Southern Access Crude Oil Pipeline
    • Enbridge
    • Expansion - Completed - Q3 - 2015
    • 454 miles, 42 inches
    • Crude
    • 150,000 bpd
    • Capacity increased from 800,000 b/d to 950,000 b/d. There are plans to expand further to 1,200,000 b/d.
  6. Line 78 Chicago Connectivity Enbridge Expansion Completed 2015 Q4 81 36 CRD 570,000 Connects Flanagan, Illinois, terminal to Griffith, Indiana, terminal (the latter was formerly the beginning of Line 78).
  7. Southern Access Crude Oil Pipeline
    • Enbridge
    • Extension - Completed - Q4 - 2015
    • 167 miles, 24 inches
    • Crude
    • 300,000 bpd
    • Goes from Flanagan to a petroleum terminal hub near Patoka (both in Illinois).
  8. Mariner South NGL Pipeline
    • Energy Transfer Partners
    • New - Completed - Q2 - 2015
    • 62 miles, 16 inches
    • Propane, n-butane
    • 200,000 bpd
    • Originating at the Lone Star terminal at Mont Belvieu and terminating at the Sunoco Logistics Nederland liquefied petroleum gas export terminal.
  9. Permian Express Crude Oil Pipelines - Line 2
    • Energy Transfer Partners
    • New - Completed - Q3 - 2015
    • 334 miles, 24 & 20 inches
    • Crude
    • 230,000 bpd
    • Garden City, Texas, to Colorado City, Texas, segment has 20-inch diameter pipeline, Colorado City to Corsicana, Texas, has 24-inch diameter pipeline.
  10. Enterprise Aegis Ethane Pipeline
    • Enterprise Products Partners
    • New - Completed - Q3 - 2015 - Section 2
    • 48 miles, 20 inches
    • Ethane
    • 360,000 bpd
    • Whole pipeline goes from Mont Belvieu, Texas, to Napoleonville, Louisiana. This is the second segment from Beaumont to Lake Charles
  11. South Texas Crude Oil Pipeline System - Rancho II Pipeline
    • Enterprise Products Partners
    • New - Completed - Q3 - 2015
    • 88 miles - 36 inches
    • Crude - 1,000,000 bpd
    • Currently connects Enterprise's Midland-to-Sealy Pipeline and the converted Red Seminole Pipeline to the Enterprise Crude Houston (ECHO) terminal in Houston, Texas. Part of the Midland-to-ECHO pipeline system.
  12. Enterprise Aegis Ethane Pipeline
    • Enterprise Products Partners
    • New - Completed - Q4 - 2015 - Section 3
    • 162 miles, 20 inches
    • Ethane
    • 360,000 bpd
    • This section goes from Lake Charles to Napoleonville, Whole pipeline goes from Mont Belvieu, Texas, to Napoleonville, Louisiana.
  13. Eagle Ford JV Pipeline System
    • Enterprise Products Partners; Plains All American
    • Expansion - Completed - 2015 - Pipeline expansion 1
    • 175 miles
    • Crude
    • 300,000 bpd
    • Capacity increased from 300,000 b/d to 600,000 b/d. Expansion included a 20-inch loop of the entire system, more pumping capacity, and a connection to the Cactus Pipeline in Gardendale, Texas.
  14. Double H Crude Oil Pipeline
    • Kinder Morgan
    • New - Completed - Q1 -2015
    • 511 miles
    • Crude - 84,000 bpd
    • Origins in both North Dakota and Montana.
  15. Thunder Creek NGL Pipeline Meritage Midstream New Completed 2015 Q2 108 8, 6 HGL Y-grade 15,000 The pipeline has a preliminary design capacity of 15,000 b/d (expandable to 30,000 b/d). The first 108-mile leg of the pipeline came into service in April 2015. This pipeline originates at the 50 Buttes Natural Gas Processing Complex near Gillette, Wyoming, and terminates at an interconnect with Phillips 66’s Powder River Pipeline near Douglas, Wyoming. The Phillips 66 Powder River Pipeline delivers natural gas liquids to Phillips 66’s fractionation and refining complex near Borger, Texas. The 50 Buttes Plant is owned by Thunder Creek Gas Services, LLC, also a wholly owned subsidiary of Meritage.
  16. South Texas Crude Oil Pipeline System - expansion phase 2
    • NuStar
    • Expansion - Completed - Q1 - 2015
    • Crude - 65,000 bpd
    • Capacity increased from 275,000 b/d to 340,000 b/d between Gardendale and Corpus Christi (both in Texas).
  17. Hutchinson-to-Medford NGL Pipeline OneOK New Completed 2015 Q2 95 16 HGL Y-grade 120,000 95-mile natural gas liquid (NGL) pipeline between existing NGL fractionation at Hutchinson, Kansas, and Medford, Oklahoma.
  18. Cactus Oil Pipeline
    • Cactus I Pipeline
    • Plains All American
    • New - Completed - Q2 - 2015
    • 298 miles - 20 inches
    • Crude - 250,000 bpd
    • Goes from McCamey to Gardendale (both in Texas).
  19. Basin Oil Pipeline
    • Basin Pipeline expansion 2
    • Plains All American
    • Expansion - Completed - 2015
    • 24 miles - 20 inches
    • Crude - 360,000 bpd
    • Mainline loop from Wink to Midland (both in Texas) looped with 24-inch diameter pipeline to bring total capacity from 240,000 b/d to 600,000 b/d.
  20. Pony Express Crude Oil Pipeline
    • Northeast Colorado lateral
    • Tallgrass Energy
    • Expansion - Completed - Q2 - 2015
    • 66 miles, Crude - 90,000 bpd
    • Goes from Weld County, Colorado, to Sterling, Colorado. This 90,000 b/d lateral joins the 230,000 b/d Pony Express Pipeline segment from Guernsey, Wyoming, to Sterling, where they both feed into the 320,000 b/d segment from Sterling to Cushing, Oklahoma.
  21. Saddlehorn Crude Oil Pipeline & Grand Mesa Crude Oil Pipeline
    • Saddlehorn/Grand Mesa Pipeline–Platteville to Cushing
    • Andarko; Magellan; Plains All American
    • Expansion - Completed - Q3 - 2016
    • 538 miles, Crude - 340,000 bpd
    • This segment goes from Platteville, Colorado, to Cushing, Oklahoma. 190,000 b/d is considered to be the Saddlehorn Pippeline, and the other 150,000 b/d is considered to be the Grand Mesa Pipeline. The second segment, from Carr, Colorado, to Platteville came online in Q1 2017.
  22. Sand Hills NGL Pipeline
    • Sand Hills NGL Pipeline expansion 2
    • DCP Midstream; Enbridge; Phillips 66
    • Expansion - Completed - Q2 - 2016
    • 260miles - 20 inches - HGL Y-grade - 30,000 bpd
    • Capacity increased from 250,000 b/d to 280,000 b/d as a result of a new pump station.
  23. Heidelberg Oil Pipeline Enbridge New Completed 2016 Q1 34 20 CRD 120,000
  24. Express Oil Pipeline System
    • Enbridge
    • Expansion - Completed - Q4 - 2016
    • 785 miles - 24 inches - Crude - 30,000 bpd
    • Capacity increased from around 250,000 b/d to 280,000 b/d. In service since 1997, purchased by Spectra in 2013. Spectra merged with Enbridge in 2017. Connects to Platte Pipeline; the two are sometimes thought of as one system.
  25. Platte Crude Oil Pipeline
    • Platte Pipeline expansion
    • Enbridge
    • Expansion - Completed - Q4 - 2016
    • 932 miles - 20 inches - Crude - 21,000 bpd
    • 164,000 b/d capacity for the first ~100 miles (Casper, Wyoming, to Guernsey, Wyoming), then down to 145,000 b/d for the remainder (Guernsey, Wyoming, to Wood River, Illinois). Originally constructed in 1952.
  26. Lone Star West Texas Gateway NGL Pipeline - phase II
    • Energy Transfer Partners
    • New - Completed - Q2 - 2016
    • 273 miles - 24 inches
    • HGL - Y-grade - 375,000 bpd
    • Baden Storage in Martin County, Texas to Meridien, Texas.
  27. Lone Star West Texas Gateway NGL Pipeline - phase I
    • Energy Transfer Partners
    • New - Completed - Q4 - 2016
    • 260 miles - 30 inches
    • HGL - Y-grade - 495,000 bpd
    • Meridien, Texas, to Mont Belvieu, Texas.
  28. Bayou Bridge Crude Oil Pipeline
    • Energy Transfer; Phillips 66
    • New - Completed - Q2 - 2016
    • 49 miles, 30 inches
    • Crude
    • 480,000 bpd
    • Phase 1 (30-inch diameter) from Nederland, Texas, to Lake Charles, Louisiana.
    • Phase 2 (24-inch diameter) completed January 2019 from Lake Charles to Saint James, Louisiana.
  29. Permian Longview and Lousiana Extension ExxonMobil; Sunoco Logistics Partners, Vitol (SunVit Pipeline JV) Expansion, Reversal Completed 2016 Q2 380 CRD 160,000 Project has three parts: new pipeline from Midland Hub, Texas, to Garden City, Texas (100,000 b/d, built by SunVit), new pipeline from Garden City to Longview, Texas (100,000 b/d, built by Sunoco), and reversal of existing pipeline so it flows from Longview, Texas, to Saint James, Louisiana (160,000 b/d, done by Exxon).
  30. Cornerstone NGL Pipeline
    • Marathon Pipeline (MPLX)
    • New - Completed - Q3 - 2016
    • 50 miles - 16 inches - HGL - Butanes, natural gasoline, condensate - 180,000 bpd
    • Provides connectivity from MarkWest Energy Partners, L.P.’s condensate stabilizer in Cadiz, Ohio, and Utica East Ohio’s fractionator in Scio, Ohio, which will serve as Cornerstone’s initial two origination points, to MPLX’s tank farm in East Sparta, Ohio, which then connects both to Marathon Petroleum Corporation’s Canton, Ohio, refinery and to other pipelines that service the Midwest.
  31. Cornerstone NGL Pipeline
    • Marathon Pipeline (MPLX)
    • New - Completed - Q3 - 2016
    • 50 miles - 16 inches - Crude - 180,000 bpd
    • Goes from Harrison County, Ohio, to a Marathon refinery in Canton, Ohio.
  32. Cornerstone NGL Pipeline
    • Marathon Pipeline (MPLX)
    • Expansion - Completed - Q4 - 2016
    • 8 miles - 16 inches - HGL - Butanes, natural gasoline, condensate - 50,000 bpd
    • Construction of another 8-mile stretch of pipeline, connecting MarkWest’s Hopedale, Ohio, fractionation facility to Cornerstone. This allowed more natural gasoline to flow into the Cornerstone Pipeline, and increasing total capacity from 180,000 b/d to 230,000 b/d.
  33. Robinson-Indiana-Ohio (RIO) Pipeline reversal Marathon Pipeline (MPLX) Reversal Completed 2016 Q4 250 8 PRD Gasoline, distillates, diluent 50,000 In December 2016, MPLX reversed the 50,000 b/d RIO Pipeline (250 miles, 8-inch diameter) to provide further distribution to the Midwest from Lima, Ohio. MPLX is currently constructing additional connectivity and expanding pipelines to provide diluent service to western Canada, which is expected to be complete in 2017.
  34. Patoka-to-Lima expansion Marathon Pipeline (MPLX) Expansion Completed 2016 302 22, 20 CRD 18,000 Capacity increased from 249,000 b/d to 267,000 b/d.
  35. NST Express Pipeline NorthStar Midstream New Completed 2016 Q4 23 CRD 40,000 Goes from Alexander to East Fairview (both in North Dakota). Bidirectional, but initially flows southwest. Expandable to 100,000 b/d.
  36. Sacagawea Pipeline Paradigm, Phillips 66 (Paradigm Midstream JV) New Completed 2016 Q4 91 16 CRD 200,000 Paradigm Midstream is a JV between Paradigm and Phillips 66. The joint ventures are developing the Palermo Rail Terminal and the Sacagawea Pipeline. The terminal began rail-car loading from truck deliveries at the end of 2015. The pipeline began operations in November 2016..
  37. Cactus Oil Pipeline
    • Cactus I Pipeline expansion 1
    • Plains All American
    • Expansion - Completed - Q4 - 2016
    • 298 miles - 20 inches
    • Crude - 50,000 bpd
    • Capacity expanded from from 250,000 b/d to about 300,000 b/d. Goes from McCamey to Gardendale (both in Texas).
  38. Red River Oil Pipeline
    • Plains All American
    • New - Completed - Q4 - 2016
    • Crude - 150,000 bpd
    • Goes from Cushing, Oklahoma, to Longview, Texas.
  39. Pinon Pipeline expansion Plains All American Expansion Completed 2016 63 20 CRD 200,000 Expanded pipeline segment between Reeves County, Texas, and Wink, Texas.
  40. Caddo Crude Oil Pipeline
    • Plains All American; Delek
    • New - Completed - Q4 - 2016
    • 80 miles - 12 inches - Crude - 80,000 bpd
    • Goes from Longview, Texas, to Shreveport, Louisiana.
  41. Rangeland Intergrated Oil System (Rio) pipeline Rangeland Energy/Tesoro Refining & Marketing New Completed 2016 Q3 110 12 CRD 125,000 110-mile, 12-inch pipe from Loving County Texas to Midland (in Midland County), Texas. Capacity to transport 125,000 b/d.
  42. Houma-to-Houston Oil Pipeline Zydeco (Ho-Ho)
    • Houma-to-Clovelly expansion
    • Shell Midstream Partners
    • Expansion - Completed - 2016
    • 34 miles - 24 - inches - Crude - 100,000 bpd
    • Increased capacity of Houma, Louisiana, to Clovelly, Louisiana, segment from 400,000 b/d to 500,000 b/d.
  43. Houma-to-Houston Oil Pipeline Zydeco (Ho-Ho)
    • Port-Neches-to-Houma expansion
    • Shell Midstream Partners
    • Expansion - Completed - 2016
    • 213 miles - 22 - inches - Crude - 15,000 bpd
    • Increased capacity of Port Neches, Texas, to Houma, Louisiana, segment from 360,000 b/d to 375,000 b/d.
  44. Delaware Basin Extension Sunoco Logistics Partners Expansion Completed 2016 Q3 125 CRD 100,000 Goes from Texas through Lea, New Mexico, and back into Texas where it ends at Midland. Expandable to 200,000 b/d.
  45. Keystone Pipeline
    • Keystone Houston Lateral
    • TC Energy
    • Expansion - Completed - Q3 - 2016
    • 48 miles - Crude - 700,000 bpd
    • Lateral from Keystone Gulf Coast Extension mainline in Liberty, Texas, to Houston, Texas.
  46. Vantage Ethane Pipeline
    • Vantage Pipeline Canada
    • Expansion - Completed - Q4 - 2016
    • 50 miles - 8 inches -HGL - Ethane - 28,000 bpd
    • Capacity increased from 40,000 b/d to 68,000 b/d as a result of additional pumps. Also added lateral to Stateline gas plant.
  47. Saddlehorn Crude Oil Pipeline & Grand Mesa Crude Oil Pipeline
    • Saddlehorn/Grand Mesa Pipeline—Carr to Platteville
    • Andarko; Magellan; Plains All American
    • Expansion - Completed - Q1 - 2017
    • 50 miles, 16 inches, Crude - 340,000 bpd
    • This segment goes from Carr, Colorado, to Platteville, Colorado. 190,000 b/d is considered to be the Saddlehorn Pipeline, and the other 150,000 b/d is considered to be the Grand Mesa Pipeline. The first segment, from Platteville to Cushing, Oklahoma, came online in Q3 2016.
  48. Sand Hills NGL Pipeline
    • Sand Hills NGL Pipeline expansion 3
    • DCP Midstream; Enbridge; Phillips 66
    • Expansion - Completed - Q4 - 2017
    • 140 miles - 20 inches - HGL Y-grade - 85,000 bpd
    • Capacity increased from 280,000 b/d to 365,000 b/d as a result of adding three pump stations and a lateral.
  49. Alberta Clipper Pipeline (Line 67) - border expansion
    • Enbridge Expansion Completed 2017
    • 3 miles - 36 inches - Crude - 350,000 bpd
    • Approved October 2017; capacity already existed from previous upgrades and was awaiting Presidential permit. Line 67 goes from Alberta, Canada to Wisconsin. This segment is the last 3 miles that connect North Dakota to the Canadian border. It brought the capacity of the pipeline at the border to about 800,000 b/d, up from 450,000 b/d, allowing the entire pipeline to then flow at 800,000 b/d. Capacity is based on heavy crude; the total capacity can be almost 890,000 b/d if the pipeline is carrying light crude.
  50. Permian Express Crude Oil Pipelines - Line 3
    • Energy Transfer Partners, ExxonMobil (Permian Express Partners JV)
    • New - Completed - Q4 - 2017
    • Crude - 140,000 bpd
    • Partial service of 100,000 b/d in Q4 2017, with the final 40,000 b/d of capacity online in Q3 2018.
  51. Dakota Access Crude Oil Pipeline
    • Energy Transfer Partners, MarEn Bakken Company (owned by Enbridge and Marathon Pipeline), Phillips 66 (Bakken Pipeline JV)
    • New - Completed - Q2 - 2017
    • 1,172 miles - 30 inxches - Crude - 525,000 bpd
    • Along with the Energy Transfer Crude Oil Pipeline, makes up the Bakken Pipeline. Expandable to 570,000 b/d.
  52. Energy Transfer Crude Oil Pipeline ETCO
    • Energy Transfer Partners, MarEn Bakken Company (owned by Enbridge and Marathon Pipeline), Phillips 66 (Bakken Pipeline JV)
    • Conversion + New - Completed - Q2 - 2017
    • 754 miles - 30 inches - Crude - 525,000 bpd
    • 686 miles converted from natural gas pipeline, with 68 miles of new build. Along with the Dakota Access Pipeline, makes up the Bakken Pipeline. Expandable to 570,000 b/d.
  53. Cajun-Sibon Ascension Pipeline EnLink; Marathon Petroleum Expansion Completed 2017 Q2 30 10 HGL Butanes, natural gasoline 130,000 Goes from EnLink’s Riverside fractionator to Marathon Petroleum’s Garyville refinery (both in Louisiana). EnLink constructed and operates the pipeline.
  54. Appalachia to Texas Ethane Pipeline (ATEX)
    • Enterprise Products Partners
    • Expansion - Completed - Q4 - 2017
    • 1,205 miles - 20, 16, 14 inches - HGL - Ethane - 20,000 bpd
    • Capacity increased from 125,000 b/d to 145,000 b/d. The first 5,000 b/d of the expansion came online sometime between 2014 and late 2017. Increased volume commitments kicking in in early 2018 spurred the capacity expansion, which was achieved with additional pumping.
  55. BridgeTex Pipeline expansion 1 Magellan; Plains All American Expansion Completed 2017 Q2 CRD 100,000 Capacity increased from 300,000 b/d to 400,000 b/d.
  56. Harpster-to-Lima Pipeline Marathon Pipeline (MPLX) New Completed 2017 Q1 50 12 PRD 50,000 The new 49-mile Harpster-to-Lima Pipeline is designed to transport condensate and natural gasoline in a batched system from Harpster, Ohio, to a tank farm in Lima, Ohio, where it can then continue on to refineries in Ohio, Michigan, Indiana, and Illinois. As part of the Utica Build-Out scope, MPLX has also expanded capacity of two product pipelines, including the East Sparta-to-Heath and Heath-to-Harpster pipelines to deliver into the new pipeline at Harpster.
  57. Cayenne Pipeline Midamerican Midstream Completed 2017 Q4 63 HGL Y-grade 40,000
  58. STACK Pipeline expansion Phillips 66, Plains All American (STACK JV) Expansion Completed 2017 Q4 90 CRD 150,000 Joint Venture between Plains all American and Phillips 66, sometimes called "STACK JV". Expansion brought capacity to 250,000 b/d (up from 100,000 b/d), and extended a portion of the pipeline for 35 miles in Oklahoma.
  59. Cactus Oil Pipeline
    • Cactus I Pipeline expansion 2
    • Plains All American
    • Expansion - Completed - Q3 - 2017
    • 298 miles - 20 inches
    • Crude - 90,000 bpd
    • Capacity increased from 300,000 b/d to 390,000 b/d. Goes from McCamey to Gardendale (both in Texas).
  60. Diamond Pipeline Plains All American; Valero New Completed 2017 Q4 440 20 CRD 200,000
  61. White Cliffs Pipeline line 2 expansion SemGroup Expansion Completed 2017 Q3 527 12 CRD 65,000 Expansion assumed on line 2. Total capacity of both White Clifff pipelines increased from 150,000 b/d to 215,000 b/d.
  62. Keystone HoustonLink Pipeline TC Energy, Magellan (HoustonLink JV) Expansion Completed 2017 Q1 9 24 CRD Connects TC Energy's Houston Terminal to Magellan system.
  63. Sand Hills NGL Pipeline
    • Sand Hills NGL Pipeline expansion 4
    • DCP Midstream; Enbridge; Phillips 66
    • Expansion - Completed - Q2 - 2018
    • 50 miles - 20 inches - HGL - Y-grade - 60,000 bpd
    • Capacity increased from 365,000 b/d to 425,000 b/d as a result of partial looping of the pipeline and the addition of seven new pump stations.
  64. Sand Hills NGL Pipeline
    • Sand Hills NGL Pipeline expansion 5
    • DCP Midstream; Enbridge; Phillips 66
    • Expansion - Completed - Q2 - 2018
    • 50 miles - 20 inches - HGL - Y-grade - 60,000 bpd
    • Capacity increased from 425,000 b/d to 485,000 b/d as a result of partial looping of the pipeline and the addition of seven new pump stations.
  65. Southern Hills Pipeline expansion 2 DCP Midstream; Enbridge; Phillips 66 Expansion Completed 2018 Q4 940 20–8 HGL Y-grade 17,000 Capacity increased from 175,000 b/d to 192,000 b/d.
  66. Stampede Oil Pipeline Enbridge New Completed 2018 Q1 16 18 CRD 100,000 Completed according to Enbridge infrastructure map. Hess platform had first oil in January 2018 and three wells completed in Q1 2018; pipeline assumed completed at the same time.
  67. Spearhead Pipeline Enbridge Other Completed 2018 Q3 650 CRD 190,000 Originally built in 2006, closed 2015 after spill, reopened in 2018.
  68. Big Foot Oil Pipeline Enbridge New Completed 2018 Q4 40 20 CRD 100,000 Big Foot platform produced first oil in November 2018.
  69. Mariner East 2 Pipeline (Hybrid) Energy Transfer Partners New Completed 2018 Q4 350 20, 16, 12 HGL Propane, butanes, natural gasoline 150,000 Partially in Service in Q4 2018 (150,000 b/d). Bypassing an uncompleted section of the pipeline with smaller-diameter, lower-pressure pipe. Permitting issues causing delay to full service .
  70. Midland-to-Sealy Pipeline Enterprise Products Partners New Completed 2018 Q2 418 24 CRD 575,000 Goes from Midland to Sealy, where it connects to the Rancho II pipeline that goes down to the Enterprise Crude Houston (ECHO) terminal in Houston (all in Texas). Together with the Rancho II pipeline, this is known as the Midland-to-ECHO 1 Pipeline System. Partial service of 540,000 b/d began in April 2018, with full service of 575,000 b/d in May 2018.
  71. Loving County Pipeline Enterprise Products Partners New Completed 2018 Q3 CRD 200,000 Goes from Lea County, New Mexico, to Midland, Texas. Expandable to 350,000 b/d.
  72. Aegis Expansion Project Enterprise Products Partners Expansion Completed 2018 Q4 299 20 HGL Ethane 40,000 Capacity expansion through pumping and "related appurtenances" plus new lateral from Napoleonville, Louisiana, to "nearby chemical plant".
  73. EPIC NGL Pipeline
    • EPIC Pipeline
    • Loving to Orla - New - Completed - Q2 - 2018
    • 65 miles - 10 inches
    • HGL - Y-grade - 220,000 bbl/day
    • Segment of the EPIC NGL Pipeline going from Loving, New Mexico, to Orla, Texas. Two out of three of the project's phases (from DLK Black River Midstream in Loving, New Mexico, to Crane, Texas) are complete and operating. The third phase goes from Crane to Corpus Christi, Texas, and is slated for completion by Q3 2019. Initially, that segment will carry crude, and will revert back to Y-grade service in Q1 2020 when the EPIC Crude Pipeline is finished and the EPIC NGL fractionator is online.
  74. EPIC NGL Pipeline
    • EPIC Pipeline
    • Orla to Crane - New - Completed - Q2 - 2018
    • 205 miles - 16 inches
    • HGL - Y-grade - 220,000 bpd
    • Segment of the EPIC NGL Pipeline going from Orla, Texas, to Crane, Texas. Two out of three of the project's phases (from Loving, New Mexico, to Crane, Texas) are complete and operating. The third segment goes from Crane to Corpus Christi, Texas, and is slated for completion by Q3 2019. Initially, that segment will carry crude, and will revert back to Y-grade service in Q1 2020 when the EPIC Crude Pipeline is finished and the EPIC NGL fractionator is online.
  75. Utopia Pipeline Kinder Morgan New Completed 2018 Q1 270 12 HGL Ethane 50,000 Expandable to 75,000 b/d.
  76. BridgeTex Pipeline expansion 2 Magellan; Plains All American Expansion Completed 2018 Q4 CRD 40,000 Capacity increased from 400,000 b/d to 440,000 b/d.
  77. Woodpat (Wood-River-to-Patoka) Pipeline expansion Marathon Pipeline (MPLX) Expansion Completed 2018 Q2 58 22 CRD 145,000 Capacity expanded from 215,000 b/d to 360,000 b/d. The expansion was in steps; capacity first increased to 345,000 b/d in mid-2018, and was up to 360,000 b/d by the end of the year. Crude oil flows onto Woodpat from the Ozark Pipeline in Wood River, Illinois. Ozark had its capacity increased to 360,000 b/d at the same time as Woodpat. Woodpat runs parallel to the Roxpat Pipeline, which is part of the same pipeline system.
  78. Ozark Pipeline expansion Marathon Pipeline (MPLX) Expansion Completed 2018 Q3 433 22 CRD 130,000 Capacity expanded from about 230,000 b/d to 360,000 b/d. Expansion was in steps; capacity first increased to 345,000 b/d in Q2 2018, and was up to 360,000 b/d by the end of the year. Connects to the Woodpat pipeline in Wood River, Illinois, which also had its capacity increased to 360,000 b/d at the same time. MPLX aquired the Ozark Pipeline from Enbridge in 2017.
  79. West Texas LPG Delaware Basin expansion 1 OneOK Expansion Completed 2018 Q3 120 16 HGL Y-grade 110,000 110,000 b/d pipeline lateral into Delaware Basin, and expansion of existing mainline system from 285,000 b/d to 395,000 b/d to accommodate the lateral volumes using looping and and two new pump stations.
  80. Sterling III expansion OneOK Expansion Completed 2018 Q4 570 16 HGL Y-grade 60,000 Capacity increased from 190,000 b/d to 250,000 b/d. Included additional natural gas liquids gathering system expansion. Connects Arbuckle Pipeline to Cajun-Sibon Pipeline in southeast Texas.
  81. Sunrise Pipeline expansion (Sunrise II) Plains All American Expansion Completed 2018 Q4 24 CRD 500,000 Sunrise had an initial capacity of 350,000 b/d from Midland, Texas, to Colorado City, Texas. The expansion increases the capacity of the Midland-Colorado segment City by 500,000 b/d, and adds a 500,000 b/d segment from Colorado City to Wichita Falls, Texas.
  82. Pony Express Crude Oil Pipeline
    • Pony Express Pipeline Platteville Extension
    • Tallgrass Energy
    • Expansion - Completed - Q2 - 2018
    • 55 miles
    • Crude - 40,000
    • Extension of Northeast Colorado lateral from Hereford, Colorado to Platteville, Colorado. Extension to have initial capacity of about 40,000 b/d, which will eventually be increased to 80,000 b/d.
  83. Pony Express Crude Oil Pipeline
    • Pony Express pump upgrades
    • Tallgrass Energy
    • Expansion - Completed - Q4 - 2018
    • 760 miles
    • Crude - 80,000
    • Pump enhancements expand capacity from 320,000 b/d to 400,000 b/d on the Guernsey, Wyoming, to Cushing, Oklahoma segment.
  84. Gray Oak Crude Oil Pipeline
    • Andeavor; Phillips 66
    • New - Completed - Q4 - 2019
    • 850 miles - Crude - 900,000 bpd
    • Pipeline goes from the Permian Basin in West Texas to both Corpus Christi and the Sweeney/Freeport area (both on the Texas Gulf Coast).
  85. Badger Pipeline ARB Midstream New Completed 2019 Q4 32 12 CRD 90,000 Orignates at Badger receipt point in southwest corner of Weld County, Colorado, and flows to Platteville, Colorado .
  86. Laurel Pipeline reversal Buckeye Partners Reversal Completed 2019 Q2 PRD 40,000 Make segement of pipeline between Altoona, Pennsylvania and Pittsburgh, Pennsylvania, bi-directional (currently, it flows west) with capacity of 40,000 b/d. Original capacity of the entire pipeline is 180,000 b/d.
  87. White Cliffs conversion DCP Midstream; Energy Transfer Conversion Completed 2019 Q4 564 12 HGL Y-grade 90,000 Conversion from 70,000 b/d crude oil pipeline. SemGroup, the operator of White Cliffs, converted a portion of their pipeline system to natural gas liquids (NGL) service and interconnected with Southern Hills Pipeline. The pipeline conversion and connection with Southern Hills provides an additional option for NGL takeaway to meet the growing needs of Colorado’s Denver-Julesburg (DJ) Basin. Expandable to 120,000 b/d. As part of the project, SemGroup constructed a 12-mile extension of White Cliffs Pipeline south of Cushing, Oklahoma to interconnect with Southern Hills. DCP also constructed a 25-mile pipeline in the DJ Basin, connecting its system to White Cliffs.
  88. Seaway Pipeline expansion 2 Enbridge; Enterprise Products Partners Expansion Completed 2019 Q1 500 30 CRD 100,000 Capacity increased from 850,000 b/d to 950,000 b/d.
  89. Permian Express 4 expansion Energy Transfer Partners, ExxonMobil (Permian Express Partners JV) Expansion Completed 2019 Q4 400 24 CRD 120,000 The Permian Express 4 expansion, which adds 120,000 barrels per day of capacity from the Permian Basin to Gulf Coast markets, went into full service on October 2019.
  90. Bayou Bridge Pipeline phase 2 Energy Transfer; Phillips 66 New Completed 2019 Q2 163 24 CRD 480,000 Phase 1 (30-inch diameter) completed April 2016 from Nederland, Texas, to Lake Charles, Louisiana. Phase 2 (24-inch diameter) from Lake Charles to Saint James, Louisiana.
  91. Midland-to-Sealy pipeline expansion Enterprise Products Partners Expansion Completed 2019 Q1 418 24 CRD 45,000 Capacity increased from 575,000 b/d to 620,000 b/d. Goes from Midland to Sealy, where it connects to the Rancho II pipeline that goes down to the Enterprise Crude Houston (ECHO) terminal in Houston (all in Texas).
  92. Seminole NGL Pipeline conversion
    • Enterprise Products Partners
    • Conversion - Completed - Q1 - 2019
    • 440 miles - 16 inches - Crude - 200,000 bpd
    • Converted part of 280,000 b/d natural gas liquid system (Seminole Red) to carry 200,000 b/d crude. Began partial service in February 2019, and is expected to be running at full capacity in April 2019. This project is the Midland-to-Sealy segment of the Midland-to-ECHO 2 Pipeline System project (the Sealy-to-ECHO segment using existing capacity on the Rancho II pipeline).
  93. Shin Oak NGL Pipeline
    • Enterprise Products Partners
    • New - Completed - Q1 - 2019
    • 624 miles - 24 inches
    • HGL - Y-grade - 250,000 bpd
    • Line brought on-stream early to accommodate volumes previously carried on Seminole Red pipeline, which was repurposed to carry crude.
  94. Shin Oak NGL Pipeline Waha lateral
    • Enterprise Products Partners
    • Expansion - Completed - Q2 - 2019
    • 34 miles - 20 inches
    • HGL - Y-grade - 445,000 bpd
    • Shin Oak, which began operations earlier this year, completed the interconnection to Waha in June, and began moving Y-grade barrels from that hub to Mont Belvieu..
  95. Shin Oak NGL Pipeline - expansion
    • Enterprise Products Partners
    • Expansion - Completed - Q4 - 2019
    • 624 miles - 24 inches
    • HGL - Y-grade - 300,000 bpd
    • Pumping stations brought online throughout 2019, reaching 550,000 b/d total pipeline capacity by Q4 2019.
  96. EPIC NGL Pipeline (Crane to Corpus Christi/Robstown)
    • EPIC Pipeline
    • New - Completed - Q3 - 2019
    • 430 miles - 24 inches
    • Crude - 400,000 bpd
    • Segment of the EPIC NGL Pipeline going from Crane to Corpus Christi/Robstown, Texas, carried crude (capacity of 400,000 b/d) initially, then reverted back to Y-grade service in Q1 2020 when the EPIC Crude Pipeline was finished and the EPIC NGL fractionator was completed.
  97. Magellan South System expansion Magellan Expansion Completed 2019 Q3 205 16, 12 PRD 140,000 135-mile, 16-inch pipeline from Houston to Hearne (both in Texas). In addition, an approximately 70-mile, 12-inch pipeline connecting terminal in Hearne and a terminal in Williamson County, Texas.
  98. Delaware Express Pipeline Medallion Pipeline New Completed 2019 Q3 60 16 CRD 250,000 60 miles of transportation pipeline, 50 more of gathering. Connects to Medallion Wolfcamp Connector System (gathering system). One report says starting at 250,000 b/d expandable to 600,000 b/d.
  99. Burgos (Dos Paises) Pipeline conversion and expansion NuStar Conversion, Expansion Completed 2019 Q3 47 8 PRD LPG, naphtha 64,000 Conversion of pipeline that previously carried just naphtha to carry refined products. The U.S. portion of the pipeline is approximately 34 miles (Peñitas, Texas and the NuStar terminal approximately 6 miles north of downtown Edinburg, Texas). The pipeline crosses under the Rio Grande. The border segment subject to the permit would extend from the center line of the Rio Grande approximately 1.6 miles to the first mainline shut-off valve in the United States. The Mexican portion of the pipeline runs approximately 12.5 miles between the Rio Grande crossing and the PEMEX Burgos Gas Plant. Project will expand product range from naphtha to naphtha plus liquefied petroleum gases and other natural gas liquids. Presidential permit granted May 2017.
  100. Permian Crude System NuStar New Completed 2019 Q3 8 30 CRD NuStar completed the second stage of its West Texas Intermediate export project, a new 8-mile, 30-inch pipeline to transport crude oil from a connection to the Plains Cactus II long-haul pipeline in Taft, Texas, to NuStar’s Corpus Christi, Texas, terminal.
  101. Valley Pipeline NuStar Expansion Completed 2019 Q3 75 12 PRD 45,000 Increased Valley Pipeline by 45,000 to 90,000 b/d. Expanded capacity by 75 miles loop segment and improvements to pump stations.
  102. Taft connector NuStar New Completed 2019 Q3 8 30 CRD 720,000 Connects from Plains All American's Cactus II Pipeline at Taft, Texas, to NuStar's North Beach terminal in Corpus Christi, Texas. Connection is expandable.
  103. Nuevo Laredo Project NuStar Expansion Completed 2019 Q3 11 8 PRD Diesel 28,000 Reactivation and expansion of existing pipeline connecting NuStar's Laredo Terminal in South Texas and its Nuevo Laredo Terminal in Tamaulipas, Mexico. The project entered partial service in Q3 2019, and expansion work on the Odem, Dos Laredos, and Nuevo Laredo pipelines (which together make up the Nuevo Laredo Project) was expected to be completed in Q1 2020. The Odem and Laredo pipelines carry product from Corpus Christi to the Laredo terminal, from which the Nuevo Laredo Pipeline brings it across the United States-Mexico border.
  104. South Texas Crude System connector NuStar New Completed 2019 Q3 16 CRD 240,000 Connects from Plains All American's Cactus II Pipeline at Taft, Texas, to NuStar's South Texas Crude System, which flows down to NuStar's North Beach terminal in Corpus Christi, Texas.
  105. Cherry Creek Pipeline OneOK Conversion Completed 2019 Q4 45 12 HGL Y-grade 50,000 Converting a natural gas pipeline to hydrocarbon gas liquid pipeline to connect the Lonesome Creek gas plant, North Dakota, to Stateline Gas Plant, North Dakota with through-access to OneOK's Elk Creek pipeline.
  106. Elk Creek Pipeline phase 1 OneOK New Completed 2019 Q3 300 20 HGL Y-grade 240,000 This is southern section of the Elk Creek Pipeline, going from the Powder River Basin in eastern Wyoming to ONEOK’s existing Mid-Continent natural gas liquids facilities in Bushton, Kansas. Intitial capacity 240,000, expansion capability up to 400,000 b/d with additional pump facilities. Completed July 2019.
  107. Elk Creek Pipeline phase 2 OneOK New Completed 2019 Q4 600 20 HGL Y-grade 240,000 This is northern section of the Elk Creek Pipeline, going from the Williston Basin (Richland County, Montana) to the Powder River Basin in eastern Wyoming. Connects to Elk Creek Phase I (completed in Q3 2019). Intitial capacity 240,000, expansion capability up to 400,000 b/d with additional pump facilities.
  108. Cactus Oil Pipeline
    • Cactus II Pipeline
    • Plains All American
    • New - Completed - Q3 - 2019
    • 575 miles - 26 inches
    • Crude - -670,000 bpd
    • Partial service in Q3 2019, full service by April 1, 2020. From Wink to Corpus Christi and Ingleside (all in Texas).
  109. Iron Horse Pipeline Tallgrass Energy; Silver Creek Midstream (Powder River Gateway JV) Conversion, New Completed 2019 Q2 80 16 CRD 100,000 80-mile, 16-inch Iron Horse pipeline will consist of 40 miles of new-build and 40 miles of gas-to-oil conversion pipeline running from Silver Creek’s Pronghorn Terminal to Guernsey (both in Wyoming) to access Tallgras Energy Pony Express crude pipeline system. The pipeline will have an initial capacity of about 100,000 b/d and is expandable up to 200,000 b/d. In-service in Q2 2019.
  110. Grand Prix Pipeline—Carlsbad lateral Targa Resources Expansion Completed 2019 Q3 90 24 HGL Y-grade 300,000 Interconnect from Carlsbad, New Mexico, natural gas processing plants to Reeves County, Texas, Grand Prix interconnect.
  111. Grand Prix Pipeline—North Texas to Mont Belvieu Targa Resources New Completed 2019 Q3 320 30 HGL Y-grade 450,000 From North Texas to Mont Belvieu on the Texas Gulf Coast. Expandable to 950,000 b/d.
  112. Grand Prix Pipeline—Reeves County to Johnson County Targa Resources New Completed 2019 Q3 400 24 HGL Y-grade 300,000 From Reeves County, Texas, to Johnson County, Texas, where it will join the Southern Oklahoma leg. Both will flow into the North Texas to Mont Belvieu leg, terminating at Targa's fractionation and storage hub.
  113. Grand Prix Extension—Southern Oklahoma Targa Resources Expansion Completed 2019 Q3 320 24–12 HGL Y-grade 200,000 Telescoping pipeline diameter with varying capacities along its length. Pipeline will diverge east in Kingfisher County to connect with natural gas plants in Coal County and Pittsburg County, Oklahoma.
  114. Matador Pipeline ARB Midstream New Completed 2020 Q2 38 CRD 220,000 Orignates in Adams County, Colorado and connects to Saddlehorn Pipeline in Platteville, Colorado, which flows southeast to Cushing, Oklahoma.
  115. Freedom Pipeline ARB Midstream New Completed 2020 Q1 12 CRD 150,000 A 12-inch, 150,000 b/d bi-directional pipeline between the Lucerne West terminal in Colorado and Platteville, Colorado. Shippers have the option to either move barrels south from Lucerne West to Platteville or move barrels gathered on the Badger and Matador systems north from Platteville to Lucerne West.
  116. Texas Express Pipeline expansion ArcLight; DCP Midstream; Enterprise Products Partners; Occidental Petroleum Expansion Completed 2020 Q2 580 20 HGL Y-grade 90,000 Capacity increased from 280,000 b/d to 370,000 b/d as a result of additional pumping to accommodate increased volumes on the Front Range Pipeline and production growth in the Anadarko region.
  117. Saddlehorn Crude Oil Pipeline & Grand Mesa Crude Oil Pipeline
    • Saddlehorn Pipeline expansion
    • Black Diamond Gathering; Magellan; Plains All American; Western Midstream
    • Expansion - Completed - Q4 - 2020
    • 538 miles - Crude - 100,000 bpd
    • The Saddlehorn Pipeline was expanded by 100,000 b/d, to a new total capacity of 290,000 b/d. Saddlehorn is a group that consist of Magellan, Plains All American, Western Midstream, and Black Diamond. Magellan serves as operator of the Saddlehorn pipeline.
  118. Equality Pipeline Bridger Pipeline (True Companies) New Completed 2020 Q3 190 24 CRD 200,000 Equality Pipeline in Wyoming traverses about 190 miles from Hulett south to Guernsey. The line has a 20-inch diameter capable of moving as much as 200,000 b/d of crude oil. Construction began in November 2019 and was completed in August 2020.
  119. Augustus Pipeline Centurion Pipeline New, Other Completed 2020 Q4 75 20,18 CRD 150,000 Approximately 75 miles of pipeline connecting Midland, Texas, to Crane, Texas. 30 miles of new 20-inch pipeline from Midland to Ector, Texas, and 45 miles of existing 18-inch pipeline from Ector to Crane.
  120. Front Range Pipeline expansion DCP Midstream, Enterprise Products Partners (Front Range Pipeline JV); Occidental Petroleum Expansion Completed 2020 Q2 435 16 HGL Y-grade 100,000 Addition of pumps along pipeline increased total capacity from 150,000 b/d to 250,000 b/d.
  121. Sand Hills NGL Pipeline
    • Sand Hills NGL Pipeline expansion 6
    • DCP Midstream; Enbridge; Phillips 66
    • Expansion - Completed - Q2 - 2020
    • 400 miles - 20 - HGL - Y-grade - 15,000 bpd
    • Capacity increased from 485,000 b/d to 500,000 b/d as a result of full looping of the pipeline.
  122. Mariner East 2X Energy Transfer Partners New Completed 2020 Q4 350 16 HGL Butanes, natural gasoline, condensate, Y-grade, refined products 250,000 The pipeline was placed into partial service in 4Q 2020 and is expected to be placed into full service in 2Q 2021. The pipeline was built roughly parallel to Mariner East 2. .
  123. Lone Star West Texas Gateway NGL Pipeline - expansion
    • Energy Transfer Partners
    • Expansion - Completed - Q3 - 2020
    • 352 miles - 24 inches
    • HGL - Y-grade - 400,000 bbl
    • Pipeline extension completed ahead of schedule in Q3 2020 instead of Q4 2020 like originally reported. Extension of the Lone Star NGL pipeline into the Permian Basin, with originations near Wink, Texas, connecting to 30-inch mainline near Fort Worth, Texas.
  124. Midland to ECHO Crude Oil Pipeline - pipeline 3
    • Enterprise Products Partners
    • New - Completed - Q3 - 2020
    • Crude - 450,000 bpd
    • Expansion of pipeline from Midland, Texas, to the Enterprise Crude Houston (ECHO) terminal in Houston, Texas.
  125. EPIC Crude Oil Pipeline
    • EPIC Pipeline
    • New - Completed - Q2 - 2020
    • 730 miles - 30 inches - Crude - 600,000 bpd
    • Construction of the 30-inch diameter crude pipeline was completed on February 26, 2020 and entered into full service on April 1, 2020. Crude will flow on the dedicated EPIC Crude pipeline at an initial capacity of 600,000 b/d (and the EPIC NGL Crane to Corpus Christi pipeline will convert to natural gas liquids service). Capacity will be expandable with additional pumping to 900,000 b/d. Remaining construction of the project is primarily focused on installing an additional 2.1 million barrels of operational storage, bringing total storage to 7.5 million barrels, as well as completing the East Dock that is expected to be operational in the second half of 2020 adding the capability of loading Suezmax vessels.
  126. EPIC NGL Pipeline—Crane to Corpus Christi/Robstown EPIC Pipeline Conversion Completed 2020 Q1 430 24 HGL Y-grade 220,000 Segment of the EPIC NGL Pipeline going from Crane to Corpus Christi/Robstown, both in Texas. Was completed Q3 2019 but initially carried crude (capacity of 400,000 b/d). Converted to Y-grade service in Q1 2020 when the EPIC Crude Pipeline was finished and the EPIC NGL fractionator was completed.
  127. Wink-to-Webster Pipeline ExxonMobil, Lotus Midstream, Delek US, Plains All American (W2W Pipeline JV) New Completed 2020 Q4 650 36 CRD 1,500,000 Owners of the Wink to Webster pipeline, announced on October 15, 2020, that the main segment of the pipeline system has started transporting Permian crude and condensate from Midland, Texas, to Houston, Texas. 650-mile, 36-inch pipeline is designed to transport approximately 1.5 million b/d of crude and condensate. The project has origin points in Wink and Midland, Texas, multiple destinations in the Houston market, including Webster, Baytown and the Enterprise Crude Houston terminal, and connectivity to Texas City and Beaumont. .
  128. Ingleside Pipeline Harvest Midstream New Completed 2020 Q2 24 24 CRD 600,000 24-mile, 24-inch oil pipeline that originates from the Harvest Midway Terminal and connects to multiple oil export terminals in the Ingleside area, including the Flint Hills Resources Ingleside Terminal and the South Texas Gateway Terminal being developed by Buckeye Partners (all in Texas). The Ingleside Pipeline also connects to multiple terminals in the Midway and Taft area. Final capacity of 600,000 b/d.
  129. Plantation Pipeline Roanoke Expansion Kinder Morgan Expansion Completed 2020 Q2 8 PRD 21,000 Increased capacity on the Plantation Pipeline by 21,000 b/d from the Baton Rouge, Louisiana, and Collins, Mississippi, origin points to the Roanoke, Virginia, area.
  130. Arbuckle II Pipeline OneOK New Completed 2020 Q1 530 30, 24 HGL Y-grade 400,000 530-mile natural gas liquids pipeline from the Mid-Continent to the Gulf Coast with initial capacity of 400,000 b/d. Expandable up to 1,000,000 b/d with additional pump facilities. More than 50% of initial capacity is contracted under long-term, fee-based agreements.
  131. West Texas LPG Delaware Basin expansion 2 OneOK Expansion Completed 2020 Q1 240 16 HGL Y-grade 80,000 Capacity increased from 395,000 b/d to 475,000 b/d as a result of additional pumping stations and complete looping.
  132. Arbuckle II Pipeline extension OneOK Extension Completed 2020 Q4 120 24 HGL Y-grade 400,000 Pipeline extended farther north and additional natural gas liquid gathering infrastructure added to increase capacity between the Mid-Continent market hub and Arbuckle II pipeline. .
  133. Red River Oil Pipeline
    • Plains All American & Delek Logistics
    • Expansion - Completed - Q3- 2020
    • 16 - Crude - 85,000 bpd
    • Expanded existing Red River Pipeline capacity from 150,000 to 235,000 b/d through additions to pumping capacity. In-service third quarter of 2020. Joint venture with Plains All American and Delek Logistics Partners.
  134. Falcon Ethane Pipeline Project Shell Midstream Partners New Completed 2020 Q4 97 16, 12, 10 HGL Ethane 107,000 97 mile system originates at MarkWest Cadiz and Utica East Ohio Scio facilities in Ohio and MarkWest Houston facilty in Pennsylvania and connects to Monaca Shell Plant in Pennyslvania.
  135. Pony Express Carpenter Extension Tallgrass Energy Expansion Completed 2020 Q2 25 12 CRD Approximately 25-mile, 12-inch pipeline connecting Carpenter, Wyoming, to existing Pony Express system at Hereford, Colorado (Platteville extension).
  136. Grand Prix Extension—Central Oklahoma and STACK Targa Resources Expansion Completed 2020 Q4 110 16 HGL Y-grade 120,000 110-mile extension of Grand Prix from southern Oklahoma into “STACK” region of Central Oklahoma where it connects with Williams’ new Bluestem Pipeline to Conway, Kansas..
  137. Bluestem Pipeline Williams New Completed 2020 Q4 189 16 HGL Y-grade 120,000 189-mile, 16-inch pipeline originating at Mid-Continent Fractionation & Storage LLC’s (MCF&S) facility in Conway, Kansas, to Kingfisher County, Oklahoma. Designed to transport 120,000 b/d of natural gas liquids, expandable to 225,000 b/d.