Summary Information

  • Ownership: HPCL LNG
  • Website: https://www.hplng.in/
  • Location: Chhara, Gujarat, India
  • Capacity: 5.0 million tons/annum
  • Status: Under construction

Brief Description

  • An onshore regasification terminal with two large tanks
  • The terminal is designed for potential expansion to 10 mtpa capacity
  • The Project shall be operated on tolling business model wherein off-takers will book capacity in the terminal

Technical Details

  • Storage capacity: 2 tanks of 200,000 m3 each
  • Unloading capacity:
  • Send out capacity:
  • Constructor:
    • Tractebel Engineering: Detailed feasibility study
    • Toyo-India: EPC work on a turnkey basis, from engineering to construction and commissioning
    • IHI Corporation & Afcons: Engineering and procurement of the entire LNG tank, mechanical construction of the tank and trial operation

Ongoing Projects/Project Status

  • Under construction
  • Commissioning is scheduled for 2023

Suppliers / Customers

  • Suppliers:
  • Customers: The customers will be gas traders who buy capacity and sell through the grid

History

  • 2107 - Environmental clearance given for the project
  • 2019 - Toyo-India awarded EPC contract
  • 2021 - HPLC became 100% owner of the project

Other Information

-

Links

  1. Tractebel Engineering LNG References
  2. TOYO Awarded LNG Regasification Project in India
  3. HPCL acquires balance 50% stake in Chhara LNG Terminal