Barcarena LNG Terminal

From A Barrel Full
Jump to navigation Jump to search

Summary Information

Brief Description

  • A floating gasification terminal based on the Energos Celsius Floating Storage Regasification Unit (FSRU) which has a nominal regasification capacity of 750 million standard cubic feet per day (mmscfd)

Technical Details

  • Storage capacity:
  • Unloading capacity:
  • Send out capacity: 750 million standard cubic feet per day (mmscfd)
  • Constructor: Seatrium

Ongoing Projects/Project Status

  • The terminal began operations in 2024

Suppliers / Customers

  • Suppliers:
  • Customers:
    • Alunorte Alumina Refinery
    • The Barcarena terminal will also supply natural gas to NFE’s 630 MW power plant from 2025.

History

  • 2021 - Gas sales agreement signed with Alunorte Alumina Refinery
  • 2023 - The FRSU was completed
  • 2024 - The terminal entered operation

Other Information

-

Links

  1. NFE and Hydro Finalize Definitive Commercial Terms for Natural Gas Supply to the Alunorte Alumina Refinery in the State of Pará, Brazil
  2. Seatrium Delivers its First FSRU Project to New Fortress Energy
  3. New Fortress Energy Places Barcarena LNG Terminal in Pará, Brazil into Operation