Summary Information

Brief Description

  • A regasification terminal

Technical Details

  • Storage capacity: three 160,000m3 full containment LNG storage tanks
  • Unloading capacity:
  • Send out capacity:
  • Constructor:
    • TGE Gas Engineering built the tanks

Ongoing Projects/Project Status

  • The project was completed in 2012

Suppliers / Customers

  • Suppliers: Qatargas is supplying the terminal
  • Customers: The regasified LNG will be fed into a proposed Zhejiang Natural Gas Grid and be connected to the local distribution network.


History

  • 2005 - CNOOC Zhejiang Ningbo LNG Co., Ltd was registered
  • 2009 - Government approval was given for the project
  • 2009 - Construction of the terminal started
  • 2012 - First cargo delivered from Qatar

Other Information

  • -

Links

  1. CIMC ENRIC LNG References
  2. CNOOC Zhejiang Ningbo LNG Co., Ltd
  3. CNOOC Clean Energy Business Progresses Well in Zhejiang and Fujian
  4. TGE Gas Engineering, LNG Tank Ningbo
  5. Qatargas delivers commissioning cargo to Zhejiang LNG Terminal in the People’s Republic of China