Abarrelfull (talk | contribs) |
||
Line 5: | Line 5: | ||
* Location: Constanza | * Location: Constanza | ||
* Capacity: | * Capacity: | ||
− | ** | + | ** Before: 3.8 million tons/annum & 76, 000 bbl/day |
− | ** | + | ** After: 5.0 million tons/annum & 100, 000 bbl/day |
* Nelson Complexity: | * Nelson Complexity: | ||
* Project Stage: Completed 2012 | * Project Stage: Completed 2012 | ||
Line 55: | Line 55: | ||
[[Category:Refinery]] | [[Category:Refinery]] | ||
[[Category:Romania]] | [[Category:Romania]] | ||
+ | [[Category:KMG]] |
Latest revision as of 11:34, 9 October 2023
Contents
Summary Information
- Ownership: Rom Petrol
- Website: http://www.rompetrol.com/
- Wiki Page: Petromidia Constanza Refinery
- Location: Constanza
- Capacity:
- Before: 3.8 million tons/annum & 76, 000 bbl/day
- After: 5.0 million tons/annum & 100, 000 bbl/day
- Nelson Complexity:
- Project Stage: Completed 2012
- Budget:
The Project
- Project Type: Upgrade and Expansion
- Project Summary: The program aims to increase by 38 percent the refinery’s crude processing capacity (from 3.6 million tons to 5 million tons per year), achieve fuel compliance with the EU standards, as well as compliance with the European environment protection regulations
- Phase 1: Revamp of FCC, Gas Desulphurization and Sulphur Recovery unit
- Phase 2: Addition of mild hydrocracker unit and hydrogen plant
- Phase 2: The Delayed Coking Unit Revamp: The estimated value of the project amounts to USD $50 million, and its completion, planned for 2012, will support both the increase in productivity of basic products and the improvement of environmental conditions.”
Main Contractors
- The works was coordinated and carried out by Rominserv, the general contractor of the Rompetrol Group,
- Licences
- ConocoPhillips provided specialized technical consulting throughout the entire project implementation.
Refining Units
- FCC - Revamp
- Delayed Coking Unit - Revamping / Expansion
- Mild hydrocracker unit - 1.7 Million Tons
- Hydrogen plant - 40,000 normal m3/hour
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
-
Products Produced
- Increased Light Products
- Euro V Gasoline & Diesel
History
- 2006 - Rompetrol announced the project
- 2008 - Technip awarded hydrogen unit contract
- 2010 - ConocoPhillips & Rompetrol announced a license and technical services agreement for the revamp of the delayed coker unit
- 2012 - The project was completed
Other Information
-
Links
- Rompetrol Rafinare plans $141 million in investments
- Rompetrol has completed the first stage of the Delayed Coking Unit Revamp
- Technip awarded contract for a hydrogen plant in Romania
- Rompetrol is finalizing the assembly works of two new units on the Petromidia platform
- ConocoPhillips, Rompetrol Rafinare S.A. and Rominserv S.A. Announce License and Technical Services Agreement for Delayed Coking
- Rompetrol Rafinare and Rompetrol Petrochemicals have successfully recommissioned the installations on the Petromidia Platform
- Rompetrol Refinery
- Rompetrol completed the assembly works of two new units on the Petromidia platform
- Petromidia Refinery – A New Beginning