* Status: In operation | * Status: In operation | ||
− | + | === Brief Description === | |
− | * The worlds first FLNG facility, PFLNG Satu is currently operating at | + | * The worlds first FLNG facility, PFLNG Satu is currently operating at [[Kanowit Gas Field]], about 180 kilometres off the coast of Bintulu, Sarawak. |
* The vessel is 300 meter-long and 60 meter-wide | * The vessel is 300 meter-long and 60 meter-wide | ||
− | + | === Technical Details === | |
* Storage capacity: | * Storage capacity: | ||
* Constructor: | * Constructor: | ||
− | + | ** **Daewoo Shipbuilding & Marine Engineering:** Vessel construction | |
− | + | ** **GE Oil & Gas:** will supply its gas turbine-driven compressor train technology | |
− | + | ** **JGC / Samsung:** FEED (Front-End Engineering and Design) | |
− | + | ** **UOP:** Providing technology for acid gas removal | |
− | + | ** **Technip:** Procurement and installation of a 3.2 kilometers flexible flowline between the existing KAKG-A central processing platform in Kanowit field to the PFLNG1 riser. It also includes modification and tie-in works at KAKG-A | |
− | * Licensor: [[ | + | * Licensor: [[LNG Terminals Using Air Products Technology | Air Products]] |
− | + | === Ongoing Projects/Project Status === | |
* The project was commissioned in [[LNG Terminal Projects Completed in 2017 | 2017]] | * The project was commissioned in [[LNG Terminal Projects Completed in 2017 | 2017]] | ||
Revision as of 14:01, 21 December 2021
Contents
Summary Information
- Ownership: Petronas
- Website: http://www.petronas.com.my/
- Location: Offshore Malaysia
- Capacity: 1.2 million tons/annum
- Status: In operation
Brief Description
- The worlds first FLNG facility, PFLNG Satu is currently operating at Kanowit Gas Field, about 180 kilometres off the coast of Bintulu, Sarawak.
- The vessel is 300 meter-long and 60 meter-wide
Technical Details
- Storage capacity:
- Constructor:
- **Daewoo Shipbuilding & Marine Engineering:** Vessel construction
- **GE Oil & Gas:** will supply its gas turbine-driven compressor train technology
- **JGC / Samsung:** FEED (Front-End Engineering and Design)
- **UOP:** Providing technology for acid gas removal
- **Technip:** Procurement and installation of a 3.2 kilometers flexible flowline between the existing KAKG-A central processing platform in Kanowit field to the PFLNG1 riser. It also includes modification and tie-in works at KAKG-A
- Licensor: Air Products
Ongoing Projects/Project Status
- The project was commissioned in 2017
Suppliers / Customers
- Suppliers: The facility is to be supplied by the [[[Kumang Cluster Gas And Condensate Fields]]]
- Customers:
+++ History
- 2012 - Technip-Daewoo Consortium (TDC), was awarded an EPCIC contract by Petronas
- 2012 - Air Products announced the signing of an equipment and process license agreement
- 2012 - JGC / Samsung awarded FEED contract
- 2013 - UOP selected for gas treatment
- 2013 - Steel cutting ceremony held for the hull
- 2014 - The first block of the keel was laid
- 2015 - Technip awarded contract to connect to gas fields
- 2016 - First gas produced
- 2017 - First cargo sold
+++ Other Information
- -
+++ Relevant Links
- Technip-Daewoo Consortium awarded a key contract for a Floating LNG unit in Malaysia
- Air Products’ LNG Expertise Selected for PETRONAS FLNG Project in Malaysia
- Petronas Selects GE’s Compressor Technology for Asia’s First Floating LNG Project
- JGC Awarded FEED Contract for Floating LNG Project in Malaysia
- Honeywell’s UOP technology selected to treat liquefied natural gas on world’s first floating facility
- Petronas Holds Steel Cutting Ceremony For Floating LNG Facility
- Petronas’ Floating LNG Facility Construction Achieves Another Milestone
- Technip awarded offshore brownfield and subsea tie-backs for PETRONAS FLNG1
- Honeywell Technology Scrubs Natural Gas on World’s First Floating LNG Vessel