Summary Information

  • Ownership: Petronas
  • Website: http://www.petronas.com.my/
  • Location: Offshore Malaysia
  • Capacity: 1.2 million tons/annum
  • Status: In operation

Brief Description

Technical Details

  • Storage capacity:
  • Constructor:
    • **Daewoo Shipbuilding & Marine Engineering:** Vessel construction
    • **GE Oil & Gas:** will supply its gas turbine-driven compressor train technology
    • **JGC / Samsung:** FEED (Front-End Engineering and Design)
    • **UOP:** Providing technology for acid gas removal
    • **Technip:** Procurement and installation of a 3.2 kilometers flexible flowline between the existing KAKG-A central processing platform in Kanowit field to the PFLNG1 riser. It also includes modification and tie-in works at KAKG-A
  • Licensor: Air Products

Ongoing Projects/Project Status

  • The project was commissioned in 2017

Suppliers / Customers

History

  • 2012 - Technip-Daewoo Consortium (TDC), was awarded an EPCIC contract by Petronas
  • 2012 - Air Products announced the signing of an equipment and process license agreement
  • 2012 - JGC / Samsung awarded FEED contract
  • 2013 - UOP selected for gas treatment
  • 2013 - Steel cutting ceremony held for the hull
  • 2014 - The first block of the keel was laid
  • 2015 - Technip awarded contract to connect to gas fields
  • 2016 - First gas produced
  • 2017 - First cargo sold
  • 2019 - The vessel moved from the Kanowit gas field to the Kebabangan Field

Other Information

  • -

Links

  1. Technip-Daewoo Consortium awarded a key contract for a Floating LNG unit in Malaysia
  2. Air Products’ LNG Expertise Selected for PETRONAS FLNG Project in Malaysia
  3. Petronas Selects GE’s Compressor Technology for Asia’s First Floating LNG Project
  4. JGC Awarded FEED Contract for Floating LNG Project in Malaysia
  5. Honeywell’s UOP technology selected to treat liquefied natural gas on world’s first floating facility
  6. Petronas Holds Steel Cutting Ceremony For Floating LNG Facility
  7. Petronas’ Floating LNG Facility Construction Achieves Another Milestone
  8. Technip awarded offshore brownfield and subsea tie-backs for PETRONAS FLNG1
  9. Honeywell Technology Scrubs Natural Gas on World’s First Floating LNG Vessel
  10. PETRONAS' First Floating LNG Facility, PFLNG Satu Sets Sail to Malaysia