Difference between revisions of "Maharaja-Lela Jamalulalam Gas and Condensate Field"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) |
||
Line 18: | Line 18: | ||
** Separation of gas and liquids. | ** Separation of gas and liquids. | ||
** Gas processed to remove mercury and CO2. | ** Gas processed to remove mercury and CO2. | ||
− | ** Delivery to | + | ** Delivery to [[Brunei LNG Terminal | BLNG]] (distance 700 m). |
− | ** | + | ** LNG is exported to LNG ship via two 16” line on a 4.5 km Jetty. |
** Liquid processed to separate and stabilise condensate and water. | ** Liquid processed to separate and stabilise condensate and water. | ||
** Delivery to BSP Seria Crude Oil Terminal (SCOT, distance 17 km). Crude oil is exported to oil tanker via Single Buoy Mooring (SBM). | ** Delivery to BSP Seria Crude Oil Terminal (SCOT, distance 17 km). Crude oil is exported to oil tanker via Single Buoy Mooring (SBM). | ||
Line 25: | Line 25: | ||
+++ Contractors | +++ Contractors | ||
* **Technip:** | * **Technip:** | ||
− | + | ** EPCC - Onshore Processing plant | |
− | + | ** Engineering, procurement, supply, construction and commissioning (EPSCC) of a new onshore pipeline, in order to transport Maharaja Lela & Jamalulalam South (MLJS) gas | |
* **Vallourec:** Supply of premium pipes the majority of which in high alloyed, corrosion-resistant grades, threaded with latest premium connections | * **Vallourec:** Supply of premium pipes the majority of which in high alloyed, corrosion-resistant grades, threaded with latest premium connections | ||
* SapuraAcergy: Provision of subsea services | * SapuraAcergy: Provision of subsea services |
Latest revision as of 13:39, 11 September 2023
Summary Information
- Operator: Total
- Country: Brunei
- Location: Block B offshore
- Production start: 1999
- Partners:
- Type: Gas & Condensate
- Estimated Reserves:
- Production Volume:
+++ Description
- Offshore facilities
- Two production wellhead platforms: MLJ-1 and MLJ-2.
- 2.5 km / 12” MLJ-2/MLJ-1 sea pipeline.
- 85 km / 18” MLJ-1/OPP sea pipeline.
- Onshore facilities
- Reception of well fluids in slugcatcher (800 m3).
- Separation of gas and liquids.
- Gas processed to remove mercury and CO2.
- Delivery to BLNG (distance 700 m).
- LNG is exported to LNG ship via two 16” line on a 4.5 km Jetty.
- Liquid processed to separate and stabilise condensate and water.
- Delivery to BSP Seria Crude Oil Terminal (SCOT, distance 17 km). Crude oil is exported to oil tanker via Single Buoy Mooring (SBM).
+++ Contractors
- **Technip:**
- EPCC - Onshore Processing plant
- Engineering, procurement, supply, construction and commissioning (EPSCC) of a new onshore pipeline, in order to transport Maharaja Lela & Jamalulalam South (MLJS) gas
- **Vallourec:** Supply of premium pipes the majority of which in high alloyed, corrosion-resistant grades, threaded with latest premium connections
- SapuraAcergy: Provision of subsea services
+++ History
- 1999 - Production started
- 2010 - Southern extension discovered
- 2014 - Technip awarded pipeline contract
+++ Geology
- The multiple reservoir levels are situated at the downthrown side of a major down-to-basin fault.
+++ Links
- Maharaja Lela - Jamalul Alam
- Maharaja, Technip
- FLASH GAS COMPRESSOR OPP PLANT, World Bank
- Serimax Asia Pipeline References
- Elf Aquitaine announces production start-up Of Maharaja-Lela field in Brunei
- Total Brunei new gas and condensate discovery in offshore Block B
- Technip awarded contract in Brunei, reinforcing its presence in the country
- Vallourec awarded important offshore contract by Total for ML-South Project in Brunei