Difference between revisions of "Guangdong Huizhou LNG Terminal"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) (→Links) |
Abarrelfull (talk | contribs) |
||
(2 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
=== Summary Information === | === Summary Information === | ||
− | * Ownership: | + | * Ownership: Guangdong Huizhou LNG |
* Website: | * Website: | ||
* Location: | * Location: | ||
Line 12: | Line 12: | ||
=== Technical Details === | === Technical Details === | ||
− | * Storage capacity: | + | * Storage capacity: 3x 200,000 m3 tanks |
* Unloading capacity: | * Unloading capacity: | ||
* Send out capacity: | * Send out capacity: | ||
* Constructor: | * Constructor: | ||
+ | ** TGE:EPC for three 200,000 m3 prestressed full containment LNG tanks | ||
=== Ongoing Projects/Project Status === | === Ongoing Projects/Project Status === | ||
− | + | * Commissioning is expected in [[LNG Terminal Projects to be Completed in 2024 | 2024]] | |
=== Suppliers / Customers === | === Suppliers / Customers === |
Latest revision as of 16:49, 6 January 2022
Contents
Summary Information
- Ownership: Guangdong Huizhou LNG
- Website:
- Location:
- Capacity: 6.2 million tons/annum
- Status: Under construction
Brief Description
- In the first phase of the project will include the construction of a jetty and three LNG storage tanks of a 200 000 m3 capacity each and will have a regasification capacity of 6.2 MTPA.
Technical Details
- Storage capacity: 3x 200,000 m3 tanks
- Unloading capacity:
- Send out capacity:
- Constructor:
- TGE:EPC for three 200,000 m3 prestressed full containment LNG tanks
Ongoing Projects/Project Status
- Commissioning is expected in 2024
Suppliers / Customers
- Suppliers:
- Customers:
History
- 2021 - Construction of the project started