Summary Information

The Project

  • Project Type: Expansion and upgrade
  • Project Summary:
    • The project, aims to expand the refinery’s crude processing capacity and to increase refining depth
    • It will produce ultra-low sulfur diesel and gasoline (diesel + 1,200,000 m3/year and gasoline + 650,000 m3/year)
  • Main Contractors:
    • Hytech: Basic and Detailed Engineering for revamp of Crude Unit and Reformer
  • Licences:

Refining Units

  • Crude unit - revamp
  • Reformer - revamp
  • Naphtha and Diesel hydrotreaters
  • Delayed coker
  • Sulfur recovery unit
  • Sour water stripper
  • Sour gas scrubbers
  • Amine regeneration system

Terminal Capacity

  • Crude Oil:
  • Refined Products:

Crude Supply

  • -

Products Produced

  • The refinery will produce much greater quantities of ULSD and Gasoline

History

  • 2016 - IFC awarded the first loan
  • 2017 - Hytec awarded basic engineering contract
  • 2019 - IFC awarded the second loan

Other Information

  • IFC has made two loans for the project
    • US$135 million of a US$500 million package in 2019
    • US$78 million of a US$378 million package in 2016

Links

  1. Hytech Downstream References
  2. Axion Energy awards Hytech a Basic and Detailed Engineering contract to develop the revamp of the Campana Refinery Powerformer and Atmospheric Distillation
  3. IFC project summary
  4. IFC helps Argentina meet energy needs with $378 million in long term loans to Axion Energy
  5. IFC helps Argentina meet energy needs with $500 million loan to Pan American Energy