Guru Gobind Singh Refinery Expansion Project
Revision as of 16:23, 19 March 2021 by Abarrelfull (talk | contribs) (Created page with "=== Summary Information === * Ownership: HMEL * Website: http://www.hmel.in/ * Wiki Page: [[[Guru Gobind Singh Refinery]]] * Location: Bathinda, Punjab, India * Capacity:...")
Contents
Summary Information
- Ownership: HMEL
- Website: http://www.hmel.in/
- Wiki Page: [[[Guru Gobind Singh Refinery]]]
- Location: Bathinda, Punjab, India
- Capacity:
* Before: 9.0 million tons/annum & 180,000 bbl/day * After: 11.2 million tons/annum & 224,000 bbl/day
- Nelson Complexity:
- Project Stage: Planned
- Expected Completion: [[[Refinery Projects to be Completed in 2017 | 2017]]]
- Budget:
The Project
- Project Type: Expansion of existing refinery
- Project Summary: HMEL plans to increase the capacity of the refinery from the current 9 MMTPA to 11.2 MMTPA through selected debottlenecking/expansion investments (the “debottlenecking/expansion project” or ”the Project”). The debottlenecking/expansion project will help increase the throughput of the refinery by 25% by making a relatively smaller investment of approximately 15% of the capital cost of the existing facility. The Project will take approximately four years to complete from award of contract (early 2013) to mechanical completion and pre-commissioning.
- Main Contractors
Refining Units
- -
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
- -
Products Produced
- -
History
- 2012 - HMEL applied for financing to IFC
Other Information
- -