Summary Information

  • Operator: Total
  • Country: Nigeria
  • Location: Oil Mining Lease (OML) 102
  • Production start:
  • Partners:
  • Type: Oil / Gas
  • Estimated Reserves:
  • Production Volume:

+++ Description

  • The platform weighs approximately 13,000 tons and it is 54m long, 47m wide and 30m high. This platform can produce an amount of 105,000 barrels of crude petroleum and 3 million m³ of natural gas
  • The associated gas of the Ofon field is compressed, evacuated to shore to the [[[Nigeria LNG Terminal]]]

+++ Contractors

  • **HHI** Offshore fixed platform
  • **McDermott:** Construction of four-level production deck
  • **Technip:** Loading, transport and installation of the topsides for the OFP2 fixed platform
  • **JDR:** Two five kilometre length subsea power cables, in addition to topside termination equipment and connection boxes
  • **Saipem:** OFP2
    • Living Quarters - Basic Engineering
    • Modifications and Tie-in Activities - Detail Engineering

+++ History

  • 2007 - HHI awarded contract for offshore fixed platform
  • 2012 - Total launches Phase 2 Development of Offshore Ofon Field
  • 2015 - Compression project completed, and flaring ended

+++ Geology

+++ Links

  1. Hyundai Heavy Industries Platform References
  2. McDermott Platform References
  3. Saipem Saipem Fixed Offshore Production Facilities Major Projects
  4. Saipem Fixed Offshore Production Facilities Engineering Refe
  5. Nigeria: Total launches Phase 2 Development of Offshore Ofon Field
  6. HHI Wins a $520 Million Platform Order from Nigeria
  7. JDR Awarded Subsea Power Cable Contract For Total Ofon Field
  8. Technip awarded contract for the loading, transport and installation of a production platform in Nigeria
  9. Nigeria: Total achieves flare-out on its operated Ofon field