Summary Information
- Ownership: Saudi Aramco
- Website: http://www.saudiaramco.com/
- Wiki Page: [[[Ras Tanura Refinery]]]
- Location: Ras Tanura, Eastern Province of Saudi Arabia
- Capacity:
- Before:27.5 million tons/annum & 550,000 bbl/day
- After: 47.5 million tons/annum & 950,000 bbl/day
- Nelson Complexity:
- Project Stage:
- Expected Completion:
- Budget: $8 Billion
The Project
- Project Type:
- Project Summary:
- Main Contractors
- WorleyParsons: Project management, front-end engineering design (FEED) development, contract bid package development, detailed design support, detailed design package preparation, and construction management services
Refining Units
- Crude distillation unit - 400,000
- Vacuum distillation unit, - 210,000
- Visbreaker crude unit, -120,000
- Continuous catalyst regenerator Reformer - 50,000
- Isomerization unit, - 20,000
- Diesel hydrotreater, - 90,000
- Hydrogen plant - 30-MMSCFD
- Sulfur Recovery Unit - 185-TPD (two trains)
- Amine regeneration unit - 820-GPM
- Sour water stripper - 225-GPM
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
- -
Products Produced
- -
History
- 2007 - WorleyParsons Awarded Services Contracts
Other Information
- -