Line 35: Line 35:
 
* 2010 - Major revamp completed, including retooling of the Catalytic Cracking unit, modernization of the Gas Desulphurization and Sulphur Recovery unit
 
* 2010 - Major revamp completed, including retooling of the Catalytic Cracking unit, modernization of the Gas Desulphurization and Sulphur Recovery unit
 
* 2012 - Expansion and upgrade project completed
 
* 2012 - Expansion and upgrade project completed
 +
* 2016 - Fire in vacuum distillation unit
  
 
=== Links ===
 
=== Links ===
Line 44: Line 45:
 
# [http://killajoules.wikidot.com/archive:rompetrol-the-first-crude-oil-vessel-unloaded-throug Rompetrol – the first crude oil vessel unloaded through the new sea terminal]  
 
# [http://killajoules.wikidot.com/archive:rompetrol-the-first-crude-oil-vessel-unloaded-throug Rompetrol – the first crude oil vessel unloaded through the new sea terminal]  
 
# [http://killajoules.wikidot.com/archive:rompetrol-refining-shifts-to-the-euro-5-standard Rompetrol Refining Shifts to the Euro 5 Standard]
 
# [http://killajoules.wikidot.com/archive:rompetrol-refining-shifts-to-the-euro-5-standard Rompetrol Refining Shifts to the Euro 5 Standard]
 +
# [https://abarrelfull.blogspot.com/2024/01/petromidia-refinery-fire-quenched.html Petromidia Refinery Fire Quenched]
  
 
[[Category:Refinery]]
 
[[Category:Refinery]]
 
[[Category:Romania]]
 
[[Category:Romania]]
 
[[Category:KMG]]
 
[[Category:KMG]]

Latest revision as of 17:37, 14 January 2024

Summary Information

Refining Units

  • Atmospheric Distillation
  • Delayed Coker - 22,000 bpd
  • Mild Hydrocracker
  • Fluidised Catalytic Cracker
  • Sulphur Recovery Unit
  • Hydrogen Unit - 40,000 normal m3/hour - Technip

Terminal Capacity

  • Crude Oil:
  • * Refined Products:

Crude Supply

  • Some of the crude oil processed is Kazakh, from parent company KMG

Products Produced

  • Gasoline, diesel and LPG and Jet A-1 fuel. Euro V diesel is produced.

Projects

Other Information

  • Petromidia is the only Romanian refinery located at the Black Sea shore, thus having the advantage of being supplied directly through the oil terminal located in the Port of Midia

History

  • 1975 - Construction begins
  • 1977 - Refinery commissioned
  • 2008 - Refinery launches production of Euro V diesel
  • 2009 - New crude unloading facilities commissioned
  • 2010 - Major revamp completed, including retooling of the Catalytic Cracking unit, modernization of the Gas Desulphurization and Sulphur Recovery unit
  • 2012 - Expansion and upgrade project completed
  • 2016 - Fire in vacuum distillation unit

Links

  1. Refinery webpage
  2. Foster Wheeler Delayed Cokers
  3. ConocoPhillips, Rompetrol Rafinare S.A. and Rominserv S.A. Announce License and Technical Services Agreement for Delayed Coking Unit Revamp for the Rompetrol Petromidia Refinery, Romania
  4. Technip awarded contract for a hydrogen plant in Romania
  5. Rompetrol Rafinare and Rompetrol Petrochemicals have successfully recommissioned the installations on the Petromidia Platform
  6. Rompetrol – the first crude oil vessel unloaded through the new sea terminal
  7. Rompetrol Refining Shifts to the Euro 5 Standard
  8. Petromidia Refinery Fire Quenched