=== Refining Units === | === Refining Units === | ||
+ | * Delayed Coking Unit (DCU) | ||
* Hydrocracking Unit (HCU), | * Hydrocracking Unit (HCU), | ||
* Hydrogen Production Unit (HPU) | * Hydrogen Production Unit (HPU) |
Revision as of 09:34, 11 January 2022
Contents
Summary Information
- Ownership: Gazprom Neft
- Website: http://www.gazprom-neft.com/
- Wiki Page: Moscow Refinery
- Location: Moscow, Russia
- Capacity: million tons/annum & 00,000 bbl/day
- Nelson Complexity:
- Project Stage: Under construction
- Expected Completion: 2024
- Budget:
The Project
- Project Type: Upgrade
- Project Summary: Addition of a delayed coker and hydrocracker complex
- Main Contractors
- CC7: The general construction contract
- Técnicas Reunidas: detail design of the delayed coker, materials and equipment purchase, new unit construction management and start-up
- DL E&C: detail design of the hydrocracker, materials and equipment purchase, new unit construction management and start-up
- Licences
Refining Units
- Delayed Coking Unit (DCU)
- Hydrocracking Unit (HCU),
- Hydrogen Production Unit (HPU)
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
-
Products Produced
-
History
- 2021 - Construction contracts were awarded