Summary Information
- Ownership: Rosneft
- Website: http://www.rosneft.com/
- Wiki Page: Komsomolsk Refinery
- Location: Komsomolsk-on-Amur, Eastern Russia
- Capacity: 8.0 million tons/annum & 160,000 bbl/day
- Nelson Complexity:
- Project Stage:
- Expected Completion: 2015
- Budget:
+++ The Project
- Project Type: Upgrade and expansion
- Project Summary: Rosneft is currently implementing a large-scale expansion and upgrade project at Komsomolsk refinery, which is scheduled to run through 2013 and is primarily aimed at:
- increasing the refinery’s capacity to 8 mln tonnes (59 mln barrels)
- increasing refining depth to 95%
- launching production of high-quality Euro-4 and Euro-5 products
- implementing process control and management systems meeting modern industrial safety and environmental standards
- establishing mechanisms to adjust the volume and quality of petroleum products in accordance with market trends and seasonal fluctuations in demand
- Main Contractors:
- **RusGasEngineering:** Construction of hydrocracking furnaces
- Licences:
- Hydrocracker - Chevron
+++ Refining Units
- Atmospheric Distillation
- Delayed Coker
- Hydrocracker
- Catalytic reforming unit (Upgrade)
+++ Terminal Capacity
- Crude Oil:
- Refined Products:
+++ Crude Supply
- The refinery processes [[[West Siberian Crude Oil]]], which is delivered via the Transneft pipeline and then by rail after reloading at the Uyar (near Krasnoyarsk) and Zuy (near Angarsk) rail junctions.
- Rosneft and Transneft have signed an agreement to jointly construct an offshoot of the [[[eastern siberia pacific ocean oil pipeline | Eastern Siberia – Pacific Ocean (ESPO) trunk pipeline]]] to feed the refinery
+++ Products Produced
- The refinery will be able to produce Euro-4 and Euro-5 products
+++ History
- 2013 - RusGasEngineering delivered hydrocracking furnaces
+++ Other Information
- -