Summary Information
- **This project has been Cancelled
- Ownership: 4Gas
- Website:
- Location: Goldboro, Nova Scotia, Canada
- Capacity: million tons/annum
- Status: Cancelled
+++ Brief Description
- The Nova Scotia Project will include three (3) LNG storage tanks with a gross capacity of 160,000 m3 each, providing a sendout capacity of 1.0 bcf/d (10.34 bcm/a). The site has sufficient space and utilities available to add three (3) additional tanks for an increased total sendout capacity of 2.0 bcf/d (20.67 bcm/a). The Goldboro site will be designed to receive LNG Carriers (LNGC's) with capacities ranging from 75,000 m3 to the largest planned LNGC's (250,000 m3).
+++ Technical Details
- Storage capacity: Three (3) LNG storage tanks with a gross capacity of 160,000 m3
- Unloading capacity: LNG Carriers from 75,000 m3 to 250,000 m3
- Send out capacity: 1.0 bcf/d (10.34 bcm/a)
- Constructor:
+++ Ongoing Projects/Project Status
- The project has been Cancelled
- The project is now to be developed as an export facility, see Goldboro LNG Export Terminal Project
+++ Suppliers / Customers
- Suppliers:
- Customers: Gas to be supplied to the [[[Maritimes and Northeast Gas Pipeline]]]
+++ History
- 2005 - 4Gas company formed
- 2008 - Project given environmental clearance
- 2010 - Project cancelled
- 2012 - Project reborn as an export facility
+++ Other Information
- -