Line 9: | Line 9: | ||
* Production Volume: | * Production Volume: | ||
− | + | === Description === | |
− | * The field was developed as a sub sea tie-back to the | + | * The field was developed as a sub sea tie-back to the [[Heather Oil And Gas Field | Heather platform]], which is situated 7km to the east of Broom |
* The field was previously known as West Heather & North Terrace | * The field was previously known as West Heather & North Terrace | ||
** The West heather structure was developed with three production wells and two water injection wells | ** The West heather structure was developed with three production wells and two water injection wells | ||
** The North Terrace structure was developed with two production wells and one water injection well. | ** The North Terrace structure was developed with two production wells and one water injection well. | ||
− | + | === Contractors === | |
* **GlobalSanatFe:** Drilling and well testing | * **GlobalSanatFe:** Drilling and well testing | ||
* **Kvaerner Oilfield Products:** supply and install a fully integrated system of subsea Christmas trees and control systems | * **Kvaerner Oilfield Products:** supply and install a fully integrated system of subsea Christmas trees and control systems | ||
* **Technip:** design, fabrication and installation of a pipe-in-pipe production flowline(1) which will be trenched and backfilled. The work also includes a subsea structure, spoolpiece(2) tie-ins, repositioning of a flexible riser(3) and rockdumping for upheaval buckling | * **Technip:** design, fabrication and installation of a pipe-in-pipe production flowline(1) which will be trenched and backfilled. The work also includes a subsea structure, spoolpiece(2) tie-ins, repositioning of a flexible riser(3) and rockdumping for upheaval buckling | ||
− | + | === History === | |
* 2002 - Positive test drilling completed | * 2002 - Positive test drilling completed |
Latest revision as of 15:30, 31 March 2022
Summary Information
- Operator: EnQuest
- Country: UK
- Location: 320 kilometres North-East of Aberdeen
- Production start: 2004
- Partners:
- Type: Oil / Gas
- Estimated Reserves: Oil reserves are estimated to be 36 million barrels
- Production Volume:
Description
- The field was developed as a sub sea tie-back to the Heather platform, which is situated 7km to the east of Broom
- The field was previously known as West Heather & North Terrace
- The West heather structure was developed with three production wells and two water injection wells
- The North Terrace structure was developed with two production wells and one water injection well.
Contractors
- **GlobalSanatFe:** Drilling and well testing
- **Kvaerner Oilfield Products:** supply and install a fully integrated system of subsea Christmas trees and control systems
- **Technip:** design, fabrication and installation of a pipe-in-pipe production flowline(1) which will be trenched and backfilled. The work also includes a subsea structure, spoolpiece(2) tie-ins, repositioning of a flexible riser(3) and rockdumping for upheaval buckling
History
- 2002 - Positive test drilling completed
- 2002 - Challenger Minerals & Palace Exploration Company farm in to the field
- 2003 - DNO announce that the West Heather and North Terrace oil accumulations, are to be defined as a single Field
- 2003 - Application made to Department of Trade and Industry
- 2003 - Kvaerner Oilfield Products won a contract to supply and install a fully integrated system of subsea Christmas trees and control systems
- 2003 - Lundin acquired the field from DNO
- 2004 - First oil production
- 2005 - Phase 2 Development Successfully Completed
- 2010 - Technip awarded augmentation pipeline contract
- 2010 - Enquest becomes owner following demerger from Lundin
- 2013 - MOL acquires a stake from Wintershall
- 2022 - MOL agrees to sell its stake to Waldorf
+++ Geology
- The lower part of the reservoir section of the field is in the Broom Formation of the Middle Jurassic Brent Group
Links
- New positive drilling results from West Heather
- DNO ASA Successful oil test on West Heather
- Farm-In Agreement on Heather Satellites
- Determination of the Broom Field
- Public notice: Broom Field Development Environmental Assessment
- Lundin Petroleum to Acquire Certain Assets of DNO in UK, Norway and Ireland
- Another multi-million dollar contract for Kvaerner Oilfield Products
- Lundin Petroleum: First Oil from the Broom Field, offshore UK
- Uk - Broom Field Phase 2 Development Successfully Completed
- Technip awarded augmentation pipeline contract at the broom field in UK North Sea
- Lundin announces intention to spin-off its UK business
- Enhancement of the exploration & production portfolio through North Sea acquisition
- MOL divests Upstream assets in the UK