Difference between revisions of "Bacalhau Oil Field"
Jump to navigation
Jump to search
Abarrelfull (talk | contribs) |
Abarrelfull (talk | contribs) (→Links) |
||
Line 24: | Line 24: | ||
=== Links === | === Links === | ||
+ | # [https://abarrelfull.blogspot.com/2022/04/modec-awarded-contract-by-equinor-to.html MODEC Awarded Contract by Equinor to Supply FPSO for offshore field in Brazil] | ||
# [https://abarrelfull.blogspot.com/2022/04/final-investment-decision-for-bacalhau.html Final investment decision for Bacalhau phase 1 in Brazil] | # [https://abarrelfull.blogspot.com/2022/04/final-investment-decision-for-bacalhau.html Final investment decision for Bacalhau phase 1 in Brazil] | ||
Revision as of 14:28, 21 April 2022
Summary Information
- Operator: Equinor
- Country: Brazil
- Location: Located 185 km from the coast of the municipality of Ilhabela/SP, in the state of São Paulo
- Production start: Expected 2024
- Partners:
- Type: Oil / Gas
- Estimated Reserves:
- Production Volume: phase 1 est 220,000 bpd
Description
- The Bacalhau field is situated across two licenses, BM-S-8 and Norte de Carcará.
- The development will consist of 19 subsea wells tied back to a floating production, storage and offloading unit (FPSO) located at the field. This will be one of the largest FPSOs in Brazil with a production capacity of 220,000 barrels per day and two million barrels in storage capacity. The stabilized oil will be offloaded to shuttle tankers and the gas from Phase 1 will be re-injected in the reservoir.
Contractors
- Modec: Pre-Front End Engineering Design (Pre-FEED) and turnkey contractor for the FPSO
History
- 2018 - MODEC was awarded a Pre-Front End Engineering Design (Pre-FEED) contract for the FPSO
- 2021 - Final investment decision
Geology
- The resource is a high-quality carbonate reservoir, containing light oil with minimal contaminants