Abarrelfull (talk | contribs) (Created page with "=== Summary Information === * Operator: AkerBP * Country: Norway * Location: Norwegian Sea * Production start: 2020 * Partners: Equinor, Wintershall, PGNIG * Type: Oil / Gas *...") |
Abarrelfull (talk | contribs) |
||
(2 intermediate revisions by the same user not shown) | |||
Line 17: | Line 17: | ||
=== Contractors === | === Contractors === | ||
− | * - | + | * Subsea 7 |
+ | ** EPCI contract for an Electrically Heat Traced Flowline (EHTF) for the 21 km tie-back to the Skarv FPSO | ||
=== History === | === History === | ||
+ | * 2017 - Subsea 7 awarded EPCI contract for phase II | ||
* 2020 - First production from phase I | * 2020 - First production from phase I | ||
* 2021 - First production from phase II | * 2021 - First production from phase II | ||
Line 27: | Line 29: | ||
=== Links === | === Links === | ||
− | # | + | # [https://abarrelfull.blogspot.com/2023/01/subsea-7-awarded-contract-offshore.html Subsea 7 awarded contract offshore Norway] |
− | + | # [https://abarrelfull.blogspot.com/2023/01/rfugl-phase-1-starts-production.html Ærfugl phase 1 starts production] | |
+ | # [https://abarrelfull.blogspot.com/2023/01/final-wells-come-on-stream-on-rfugl.html Final wells come on stream on Ærfugl] | ||
[[category:Field]] | [[category:Field]] | ||
[[category:Norway]] | [[category:Norway]] | ||
[[category:AkerBP]] | [[category:AkerBP]] |
Latest revision as of 10:57, 6 January 2023
Summary Information
- Operator: AkerBP
- Country: Norway
- Location: Norwegian Sea
- Production start: 2020
- Partners: Equinor, Wintershall, PGNIG
- Type: Oil / Gas
- Estimated Reserves: The reservoir holds a total of around 300 million barrels of producible oil equivalent
- Production Volume:
Description
- The Ærfugl reservoir (formerly called Snadd) was discovered in 2000 and is located just west of Skarv
- The Ærfugl development is a major subsea project in two phases. Six horizontal gas wells are tied into the existing production vessel (FPSO) on the Skarv field
- The field consists of subsea installations and is enabled by two new technologies in particular:
- More efficient reservoir drainage through new vertical X-mas trees.
- Long-distance, electrically heated flow lines to avoid hydrates in the gas pipelines. This technology significantly improves heat efficiency compared with regular technology and enables longer tie-backs.
Contractors
- Subsea 7
- EPCI contract for an Electrically Heat Traced Flowline (EHTF) for the 21 km tie-back to the Skarv FPSO
History
- 2017 - Subsea 7 awarded EPCI contract for phase II
- 2020 - First production from phase I
- 2021 - First production from phase II
Geology
- The reservoir is located 2,800 meters below the seabed. There is gas in the reservoir, but some oil will also precipitate when it is produced up to atmospheric pressure.